| Bids For: | Location: | Big Creek State Park | Date: 3/15/2012 | Project No. |
| 3 Boat Ramps | County: | POLK | Time: 11:00 A.M. | 12-02-77-04 |
1 | 2 | 3 | |||||||||||
| Estimated Cost: $185,000.00 | Contractor: | TK Concrete Inc | Joiner Construction | MPS Engineers | |||||||||
| Funding Source: 50% Federal-Boat Safety (Coast Guard), 50% Marine Fuel Tax, | 1608 Fifield Rd PO Box 111 | 11996 490th | 1444 Illinois Street | ||||||||||
| Pella IA 50219 | Plano IA 52581 | Des Moines IA 50316 | |||||||||||
| Plan Sets Requested: 8 | Quantities | 641-628-4590 | 641-649-2646 | 515-221-9832 | |||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Mobilization | 1 | L.S. | $7,500.00 | $7,500.00 | $10,000.00 | $10,000.00 | $19,000.00 | $19,000.00 | ||||
| 2 | Concrete Removal | 675 | S.Y. | $6.00 | $4,050.00 | $13.50 | $9,112.50 | $5.00 | $3,375.00 | ||||
| 3 | 6" PCC, Class C | 715 | S.Y. | $45.00 | $32,175.00 | $32.00 | $22,880.00 | $48.50 | $34,677.50 | ||||
| 4 | Riprap, Class D | 226 | Tons | $34.50 | $7,797.00 | $46.00 | $10,396.00 | $40.00 | $9,040.00 | ||||
| 5 | Crushed Stone, Class A | 62 | Tons | $25.00 | $1,550.00 | $25.00 | $1,550.00 | $25.00 | $1,550.00 | ||||
| 6 | Beach Rain Garden | 1 | L.S. | $2,500.00 | $2,500.00 | $5,000.00 | $5,000.00 | $2,000.00 | $2,000.00 | ||||
| 7 | East Rain Garden | 1 | L.S. | $3,180.00 | $3,180.00 | $5,000.00 | $5,000.00 | $2,500.00 | $2,500.00 | ||||
| 8 | West Rain Garden | 1 | L.S. | $2,500.00 | $2,500.00 | $5,000.00 | $5,000.00 | $1,500.00 | $1,500.00 | ||||
| 9 | Site Restoration | 1 | L.S. | $5,000.00 | $5,000.00 | $3,000.00 | $3,000.00 | $2,500.00 | $2,500.00 | ||||
| $66,252.00 | $71,938.50 | $76,142.50 | |||||||||||
4 | 5 | 6 | |||||||||||
| Estimated Cost: $185,000.00 | Contractor: | Ag & Turf Construction LLC | C L Carroll Company Inc | Alliance Construction Group LLC | |||||||||
| Funding Source: 50% Federal-Boat Safety (Coast Guard), 50% Marine Fuel Tax, | 17520 110th Avenue | 3623 6th Ave | 3000 S.E. Grimes Blvd, ste 800 | ||||||||||
| Davenport IA 52804 | Des Moines IA 50313 | Grimes IA 50111 | |||||||||||
| Plan Sets Requested: 8 | Quantities | 563-349-2089 | 515-282-7495 | 515-225-6677 | |||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Mobilization | 1 | L.S. | $10,000.00 | $10,000.00 | $12,500.00 | $12,500.00 | $10,000.00 | $10,000.00 | ||||
| 2 | Concrete Removal | 675 | S.Y. | $9.38 | $6,331.50 | $38.00 | $25,650.00 | $12.00 | $8,100.00 | ||||
| 3 | 6" PCC, Class C | 715 | S.Y. | $56.25 | $40,218.75 | $68.00 | $48,620.00 | $68.00 | $48,620.00 | ||||
| 4 | Riprap, Class D | 226 | Tons | $40.00 | $9,040.00 | $28.00 | $6,328.00 | $47.00 | $10,622.00 | ||||
| 5 | Crushed Stone, Class A | 62 | Tons | $27.50 | $1,705.00 | $21.00 | $1,302.00 | $46.00 | $2,852.00 | ||||
| 6 | Beach Rain Garden | 1 | L.S. | $8,125.00 | $8,125.00 | $4,730.00 | $4,730.00 | $10,000.00 | $10,000.00 | ||||
| 7 | East Rain Garden | 1 | L.S. | $8,125.00 | $8,125.00 | $5,500.00 | $5,500.00 | $13,000.00 | $13,000.00 | ||||
| 8 | West Rain Garden | 1 | L.S. | $8,125.00 | $8,125.00 | $3,850.00 | $3,850.00 | $11,000.00 | $11,000.00 | ||||
| 9 | Site Restoration | 1 | L.S. | $5,625.00 | $5,625.00 | $7,150.00 | $7,150.00 | $6,500.00 | $6,500.00 | ||||
| $97,295.25 | $115,630.00 | $120,694.00 | |||||||||||
7 | 8 | 9 | |||||||||||
| Estimated Cost: $185,000.00 | Contractor: | Con-Struct Inc | Jenco Construction | Elder Corp | |||||||||
| Funding Source: 50% Federal-Boat Safety (Coast Guard), 50% Marine Fuel Tax, | 305 S Dayton Ave | 6804 NW 2nd Street | 5088 E University | ||||||||||
| Ames IA 50010 | Des Moines IA 50313 | Des Moines IA 50327 | |||||||||||
| Plan Sets Requested: 8 | Quantities | 515-232-6443 | 515-289-2235 | 515-266-3111 | |||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Mobilization | 1 | L.S. | $12,453.00 | $12,453.00 | $30,000.00 | $30,000.00 | $25,000.00 | $25,000.00 | ||||
| 2 | Concrete Removal | 675 | S.Y. | $6.00 | $4,050.00 | $20.00 | $13,500.00 | $4.75 | $3,206.25 | ||||
| 3 | 6" PCC, Class C | 715 | S.Y. | $84.20 | $60,203.00 | $50.00 | $35,750.00 | $120.00 | $85,800.00 | ||||
| 4 | Riprap, Class D | 226 | Tons | $48.00 | $10,848.00 | $45.00 | $10,170.00 | $50.00 | $11,300.00 | ||||
| 5 | Crushed Stone, Class A | 62 | Tons | $61.00 | $3,782.00 | $30.00 | $1,860.00 | $30.00 | $1,860.00 | ||||
| 6 | Beach Rain Garden | 1 | L.S. | $12,160.00 | $12,160.00 | $48,000.00 | $48,000.00 | $28,000.00 | $28,000.00 | ||||
| 7 | East Rain Garden | 1 | L.S. | $17,105.00 | $17,105.00 | $48,000.00 | $48,000.00 | $50,000.00 | $50,000.00 | ||||
| 8 | West Rain Garden | 1 | L.S. | $15,992.00 | $15,992.00 | $48,000.00 | $48,000.00 | $38,000.00 | $38,000.00 | ||||
| 9 | Site Restoration | 1 | L.S. | $6,296.00 | $6,296.00 | $20,000.00 | $20,000.00 | $18,000.00 | $18,000.00 | ||||
| $142,889.00 | $255,280.00 | $261,166.25 | |||||||||||
10 | 11 | 12 | |||||||||||
| Estimated Cost: $185,000.00 | Contractor: | Jensen Construction Co | |||||||||||
| Funding Source: 50% Federal-Boat Safety (Coast Guard), 50% Marine Fuel Tax, | 5550 NE 22nd St Box 3345 | ||||||||||||
| Des Moines IA 50313 | |||||||||||||
| Plan Sets Requested: 8 | Quantities | 515-266-5173 | |||||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Mobilization | 1 | L.S. | $26,000.00 | $26,000.00 | $0.00 | $0.00 | ||||||
| 2 | Concrete Removal | 675 | S.Y. | $24.00 | $16,200.00 | $0.00 | $0.00 | ||||||
| 3 | 6" PCC, Class C | 715 | S.Y. | $100.00 | $71,500.00 | $0.00 | $0.00 | ||||||
| 4 | Riprap, Class D | 226 | Tons | $60.00 | $13,560.00 | $0.00 | $0.00 | ||||||
| 5 | Crushed Stone, Class A | 62 | Tons | $45.00 | $2,790.00 | $0.00 | $0.00 | ||||||
| 6 | Beach Rain Garden | 1 | L.S. | $37,000.00 | $37,000.00 | $0.00 | $0.00 | ||||||
| 7 | East Rain Garden | 1 | L.S. | $47,000.00 | $47,000.00 | $0.00 | $0.00 | ||||||
| 8 | West Rain Garden | 1 | L.S. | $39,000.00 | $39,000.00 | $0.00 | $0.00 | ||||||
| 9 | Site Restoration | 1 | L.S. | $17,500.00 | $17,500.00 | $0.00 | $0.00 | ||||||
| $270,550.00 | $0.00 | $0.00 | |||||||||||