IOWA DEPARTMENT OF NATURAL RESOURCES |
|
| Bids For: | Location: | Summerset State Park | Date: 3/8/2012 | Project No. |
| Shoulder Repairs | County: | WARREN | Time: 3:00 p.m. | 11-05-91-9 |
1 | 2 | 3 | |||||||||||
| Estimated Cost: $12,000.00 | Contractor: | Haworth Land Construction | TK Concrete Inc | Richards Construction Co Inc | |||||||||
| Funding Source: 100% Park & Institutional Road Fund, | 12981 Quaker St | 1608 Fifield Rd PO Box 111 | 2721 Sierra Ave | ||||||||||
| Indianola IA 50125 | Pella IA 50219 | Sac City IA 50583 | |||||||||||
| Plan Sets Requested: 0 | Quantities | 515-249-4747 | 641-628-4590 | 712-662-4421 | |||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Earthfill, shoulder repair | 70 | C.Y. | $20.93 | $1,465.10 | $30.00 | $2,100.00 | $10.00 | $700.00 | ||||
| 2 | Excavation, Class 20, Culvert | 30 | C.Y. | $17.34 | $520.20 | $10.00 | $300.00 | $10.00 | $300.00 | ||||
| 3 | Concrete, Class "C" Paving Patch, 6" Thick | 10 | S.Y. | $112.00 | $1,120.00 | $65.00 | $650.00 | $200.00 | $2,000.00 | ||||
| 4 | Special Backfill, Class "A" Cr. Stone | 9 | Tons | $32.27 | $290.43 | $30.00 | $270.00 | $60.00 | $540.00 | ||||
| 5 | Revetment, Class "D" Riprap | 165 | Tons | $33.91 | $5,595.15 | $37.00 | $6,105.00 | $50.00 | $8,250.00 | ||||
| 6 | Pipe, Ductile Iron, 12" Diameter | 70 | L.F. | $50.50 | $3,535.00 | $75.00 | $5,250.00 | $70.00 | $4,900.00 | ||||
| 7 | Engineering Fabric | 150 | S.Y. | $1.04 | $156.00 | $2.00 | $300.00 | $3.00 | $450.00 | ||||
| $12,681.88 | $14,975.00 | $17,140.00 | |||||||||||
4 | 5 | 6 | |||||||||||
| Estimated Cost: $12,000.00 | Contractor: | Godby Land Improvements LLC | |||||||||||
| Funding Source: 100% Park & Institutional Road Fund, | 2569 - 560th Ave | ||||||||||||
| Albia IA 52531 | |||||||||||||
| Plan Sets Requested: 0 | Quantities | 641-895-0505 | |||||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Earthfill, shoulder repair | 70 | C.Y. | $40.00 | $2,800.00 | $0.00 | $0.00 | ||||||
| 2 | Excavation, Class 20, Culvert | 30 | C.Y. | $50.00 | $1,500.00 | $0.00 | $0.00 | ||||||
| 3 | Concrete, Class "C" Paving Patch, 6" Thick | 10 | S.Y. | $100.00 | $1,000.00 | $0.00 | $0.00 | ||||||
| 4 | Special Backfill, Class "A" Cr. Stone | 9 | Tons | $40.00 | $360.00 | $0.00 | $0.00 | ||||||
| 5 | Revetment, Class "D" Riprap | 165 | Tons | $40.00 | $6,600.00 | $0.00 | $0.00 | ||||||
| 6 | Pipe, Ductile Iron, 12" Diameter | 70 | L.F. | $70.00 | $4,900.00 | $0.00 | $0.00 | ||||||
| 7 | Engineering Fabric | 150 | S.Y. | $2.00 | $300.00 | $0.00 | $0.00 | ||||||
| $17,460.00 | $0.00 | $0.00 | |||||||||||