IOWA DEPARTMENT OF NATURAL RESOURCES
ENGINEERING BUREAU

INFORMAL BID TAB
NOTICE: This document represents bids that were opened on the letting date and may be subject to further review. This is not the official bid tab.

 Bids For:  Location:   Sweet Marsh/Martens Lake  Date: 6/13/2011  Project No.  
  install water structure  County:   BREMER  Time: 3:00 p.m.  11-03-09-02

 

 
1
2
3
Estimated Cost: $24,000.00
Contractor: 
Browns Pump ServiceNate Moeller Construction LLCMatt Construction Inc
Funding Source: 50% F&W Trust - Other, 50% F&W Trust - Other, 638 Upper St
Box 89
706 7th Ave SW
203 Y Ave
Arlington IA  50606-0089Tripoli IA  50676Sumner IA  50674
Plan Sets Requested: 0
Quantities
563-633-3365319-882-3600563-578-8418
No.Description:No.UnitUnit Price AmountUnit Price AmountUnit Price Amount
1Mobilization1L.S.$2,080.00$2,080.00 $1,500.00$1,500.00 $4,500.00$4,500.00 
2PC Concrete Riser & Cover1Each$5,180.00$5,180.00 $3,625.00$3,625.00 $4,000.00$4,000.00 
3Culvert, 36" diameter, 2000D, with Type 2 Connectors80L.F.$90.00$7,200.00 $120.00$9,600.00 $100.00$8,000.00 
4Seepage Diaphragm 7'x7"2Each$300.00$600.00 $1,100.00$2,200.00 $1,000.00$2,000.00 
5Outlet Pipe Support, as per plan2Each$125.00$250.00 $500.00$1,000.00 $500.00$1,000.00 
6Stop Log, 2"x6" (nom.) treated wood, tongue & groove16Each$70.00$1,120.00 $9.50$152.00 $10.00$160.00 
7Imported clay fill150C.Y.$16.80$2,520.00 $16.00$2,400.00 $20.00$3,000.00 
8Revetment, Class D Riprap50Tons$20.00$1,000.00 $39.00$1,950.00 $20.00$1,000.00 
9Base, Crushed Stone50Tons$15.00$750.00 $19.75$987.50 $20.00$1,000.00 
      $20,700.00  $23,414.50  $24,660.00 
 



 

10/13/2026