IOWA DEPARTMENT OF NATURAL RESOURCES |
|
| Bids For: | Location: | Kiowa Marsh Wetland Complex Heindenreich WMA | Date: 6/16/2011 | Project No. |
| Repair piping in wetland dike | County: | SAC | Time: 3:00 p.m. | 11-01-81-03 |
1 | 2 | 3 | |||||||||||
| Estimated Cost: $10,000.00 | Contractor: | Richards Construction Co Inc | |||||||||||
| Funding Source: 100% F&W Trust - Other, | 2721 Sierra Ave | ||||||||||||
| Sac City IA 50583 | |||||||||||||
| Plan Sets Requested: 0 | Quantities | 712-662-4421 | |||||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Mobilization | 1 | L.S. | $1,500.00 | $1,500.00 | $0.00 | $0.00 | ||||||
| 2 | Site Preparation | 1 | L.S. | $750.00 | $750.00 | $0.00 | $0.00 | ||||||
| 3 | Excavation | 1 | L.S. | $4,500.00 | $4,500.00 | $0.00 | $0.00 | ||||||
| 4 | Sheet Pile Materials | 130 | S.F. | $17.00 | $2,210.00 | $0.00 | $0.00 | ||||||
| 5 | Sheet Pile Installation | 130 | S.F. | $21.00 | $2,730.00 | $0.00 | $0.00 | ||||||
| 6 | 3/4" to 1-1/2" Clear Rock | 88 | Tons | $51.00 | $4,488.00 | $0.00 | $0.00 | ||||||
| $16,178.00 | $0.00 | $0.00 | |||||||||||