IOWA DEPARTMENT OF NATURAL RESOURCES |
|
| Bids For: | Location: | Honey Creek Resort | Date: 1/5/2012 | Project No. |
| Wedge Dock | County: | APPANOOSE | Time: 3:00 p.m. | 11-05-04-16 |
1 | 2 | 3 | |||||||||||
| Estimated Cost: $16,000.00 | Contractor: | Hanson Contrstruction, LLC | Co-line Welding, Inc | C L Carroll Company Inc | |||||||||
| Funding Source: 100% Marine Fuel Tax, | P.O. Box 614 | 1041 Cordova | 3623 6th Ave | ||||||||||
| Clear Lake IA 50428 | Lynnville IA 50153 | Des Moines IA 50313 | |||||||||||
| Plan Sets Requested: 0 | Quantities | 641-357-8171 | 641-594-3343 | 515-282-7495 | |||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Wedge Dock | 1 | L.S. | $12,500.00 | $12,500.00 | $13,806.58 | $13,806.58 | $19,000.00 | $19,000.00 | ||||
| $12,500.00 | $13,806.58 | $19,000.00 | |||||||||||