IOWA DEPARTMENT OF NATURAL RESOURCES |
|
| Bids For: | Location: | Lake Ahquabi | Date: 11/3/2011 | Project No. |
| demo / utility installation | County: | WARREN | Time: 3:00 p.m. | 11-05-91-08 |
1 | 2 | 3 | |||||||||||
| Estimated Cost: $50,000.00 | Contractor: | Vanderpool Plumbing & Heating | HANSON CONSTRUCTION LLC | ||||||||||
| Funding Source: 100% I-JOBS, | 506 E Euclid | PO Box 614 | |||||||||||
| Indianola IA 50125 | Clear Lake IA 50614 | ||||||||||||
| Plan Sets Requested: 0 | Quantities | 5159616796 | 641-357-8171 | ||||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Shower Building Demolition | 1 | L.S. | $9,850.00 | $9,850.00 | $3,500.00 | $3,500.00 | $0.00 | |||||
| 2 | Pit Latrine Demolition | 1 | L.S. | $2,700.00 | $2,700.00 | $1,500.00 | $1,500.00 | $0.00 | |||||
| 3 | Class C4 Concrete Paving, 6" Depth | 159 | S.Y. | $26.42 | $4,200.78 | $35.00 | $5,565.00 | $0.00 | |||||
| 4 | Class "A" Cr. Stone Base Material | 186 | Tons | $19.40 | $3,608.40 | $42.00 | $7,812.00 | $0.00 | |||||
| 5 | Shower Building Site Work & Connections | 1 | L.S. | $9,390.00 | $9,390.00 | $12,500.00 | $12,500.00 | $0.00 | |||||
| 6 | Electrical Work | 1 | L.S. | $10,260.00 | $10,260.00 | $15,000.00 | $15,000.00 | $0.00 | |||||
| $40,009.18 | $45,877.00 | $0.00 | |||||||||||
10/13/2026