IOWA DEPARTMENT OF NATURAL RESOURCES |
|
| Bids For: | Location: | Kettleson-Hogsback WMA | Date: 6/21/2012 | Project No. |
| Grover's Lake Renovation | County: | DICKINSON | Time: 11:00 a.m. | 12-01-30-01 |
1 | 2 | 3 | |||||||||||
| Estimated Cost: $115,000.00 | Contractor: | Richards Construction Co Inc | Redings Gravel & Excavating | Graves Construction Co., Inc. | |||||||||
| Funding Source: 100% F&W Trust-Wildlife Habitat Stamp, | 2721 Sierra Ave | 2001 East Oak St PO Box 158 | 1810 340th Street PO Box 1417 | ||||||||||
| Sac City IA 50583 | Algona IA 50511 | Spencer IA 51301 | |||||||||||
| Plan Sets Requested: 6 | Quantities | 712-662-4421 | 515-295-3661 | 712-262-2403 | |||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Mobilization | 1 | L.S. | $7,000.00 | $7,000.00 | $4,900.00 | $4,900.00 | $25,000.00 | $25,000.00 | ||||
| 2 | Clearing & Grubbing | 1 | L.S. | $1,500.00 | $1,500.00 | $2,370.00 | $2,370.00 | $1,500.00 | $1,500.00 | ||||
| 3 | Remove Existing Intake and WCS | 1 | L.S. | $2,000.00 | $2,000.00 | $5,790.00 | $5,790.00 | $500.00 | $500.00 | ||||
| 4 | Excavation, Inlet Channel | 3877 | C.Y. | $5.00 | $19,385.00 | $4.49 | $17,407.73 | $5.10 | $19,772.70 | ||||
| 5 | Excavation, Outlet Channel Cleaning | 264 | C.Y. | $4.00 | $1,056.00 | $12.00 | $3,168.00 | $4.00 | $1,056.00 | ||||
| 6 | 10'x8' Precast RCB w/ Curbs | 30 | L.F. | $775.00 | $23,250.00 | $770.60 | $23,118.00 | $789.00 | $23,670.00 | ||||
| 7 | 10'x8' Open Top RCB w/ Buttress Wall | 6 | L.F. | $1,500.00 | $9,000.00 | $1,952.69 | $11,716.14 | $1,685.00 | $10,110.00 | ||||
| 8 | 10' Wide Precast RCB End Sections | 30 | L.F. | $725.00 | $21,750.00 | $796.14 | $23,884.20 | $1,275.00 | $38,250.00 | ||||
| 9 | Precast Cutoff Walls | 2 | Each | $3,500.00 | $7,000.00 | $4,614.50 | $9,229.00 | $2,850.00 | $5,700.00 | ||||
| 10 | Granular Bedding | 25 | Tons | $47.50 | $1,187.50 | $74.00 | $1,850.00 | $25.00 | $625.00 | ||||
| 11 | RipRap (Class E) | 80 | Tons | $57.50 | $4,600.00 | $79.00 | $6,320.00 | $55.00 | $4,400.00 | ||||
| 12 | Galvanized Steel Catwalk Components | 1 | L.S. | $7,000.00 | $7,000.00 | $15,126.00 | $15,126.00 | $14,850.00 | $14,850.00 | ||||
| 13 | Aluminum Stoplog/Fish Finger Guides | 1 | L.S. | $5,000.00 | $5,000.00 | $8,406.80 | $8,406.80 | $15,120.00 | $15,120.00 | ||||
| 14 | Aluminum Stoplogs w/ Lifting Hook | 1 | L.S. | $4,000.00 | $4,000.00 | $7,401.80 | $7,401.80 | $14,310.00 | $14,310.00 | ||||
| 15 | Aluminum Fish Fingers w/ Winch Assembly | 1 | L.S. | $7,500.00 | $7,500.00 | $9,931.90 | $9,931.90 | $17,212.50 | $17,212.50 | ||||
| 16 | Seeding & Mulching | 1 | L.S. | $3,500.00 | $3,500.00 | $4,375.00 | $4,375.00 | $5,000.00 | $5,000.00 | ||||
| $124,728.50 | $154,994.57 | $197,076.20 | |||||||||||