IOWA DEPARTMENT OF NATURAL RESOURCES
ENGINEERING BUREAU

INFORMAL BID TAB
NOTICE: This document represents bids that were opened on the letting date and may be subject to further review. This is not the official bid tab.

 Bids For:  Location:   Clear Lake State Park  Date: 3/10/2011  Project No.  
  Building Demolition  County:   CERRO GORDO  Time: 3:00 p.m.  11-03-17-03

 

 
1
2
3
Estimated Cost: $10,000.00
Contractor: 
Godby Land Improvements LLCBurr Oak Springs LimitedHolland Contracting Corp
Funding Source: 100% I-JOBS, 2569 - 560th Ave
2113 County Rd W-14
1400 S 4th St
Albia IA  52531Ridgeway IA  52165Forest City IA  50436
Plan Sets Requested: 0
Quantities
641-895-0505563-737-3510641-585-2231
No.Description:No.UnitUnit Price AmountUnit Price AmountUnit Price Amount
1Mobilization1L.S.$400.00$400.00 $1,000.00$1,000.00 $1,300.00$1,300.00 
2Brick Restroom Building Removal & Disposal1L.S.$4,000.00$4,000.00 $3,500.00$3,500.00 $3,698.40$3,698.40 
      $4,400.00  $4,500.00  $4,998.40 
 
 
4
5
6
Estimated Cost: $10,000.00
Contractor: 
Larson Contracting Central LLCHanson Construction LLC
Funding Source: 100% I-JOBS, 508 W Main St
PO Box 614

Lake Mills IA  50450Clear Lake IA  50428  
Plan Sets Requested: 0
Quantities
641-592-8610641-357-8171
No.Description:No.UnitUnit Price AmountUnit Price AmountUnit Price Amount
1Mobilization1L.S.$769.00$769.00 $3,400.00$3,400.00 $0.00 
2Brick Restroom Building Removal & Disposal1L.S.$13,500.00$13,500.00 $21,500.00$21,500.00 $0.00 
      $14,269.00  $24,900.00  $0.00 
 



 

10/13/2026