| Bids For: | Location: | Clear Lake State Park | Date: 3/10/2011 | Project No. |
| Shower Blding Pad | County: | CERRO GORDO | Time: 3:00 p.m. | 11-03-17-02 |
1 | 2 | 3 | |||||||||||
| Estimated Cost: $15,000.00 | Contractor: | Larson Contracting Central LLC | Hanson Construction LLC | ||||||||||
| Funding Source: 100% I-JOBS, | 508 W Main St | PO Box 614 | |||||||||||
| Lake Mills IA 50450 | Clear Lake IA 50428 | ||||||||||||
| Plan Sets Requested: 0 | Quantities | 641-592-5800 | 641-357-8171 | ||||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Mobilization | 1 | L.S. | $876.00 | $876.00 | $2,500.00 | $2,500.00 | $0.00 | |||||
| 2 | Construct Building Foundation As Per Plan | 1 | L.S. | $18,134.00 | $18,134.00 | $18,480.00 | $18,480.00 | $0.00 | |||||
| 3 | Granular Backfill Material | 100 | Tons | $4.68 | $468.00 | $35.00 | $3,500.00 | $0.00 | |||||
| 4 | Seeding | 1 | L.S. | $1,000.00 | $1,000.00 | $800.00 | $800.00 | $0.00 | |||||
| 5 | Sidewalk, PCC 6" | 660 | S.F. | $6.72 | $4,435.20 | $6.00 | $3,960.00 | $0.00 | |||||
| $24,913.20 | $29,240.00 | $0.00 | |||||||||||