| Bids For: | Location: | Dewey's Pasture - Thu WRP Tract | Date: 9/1/2011 | Project No. |
| Wetland Restoration Project | County: | PALO ALTO | Time: 3:00 p.m. | 11-01-74-02 |
1 | 2 | 3 | |||||||||||
| Estimated Cost: $85,500.00 | Contractor: | Redings Gravel & Excavating | Valley Contracting Inc | Richards Construction Co Inc | |||||||||
| Funding Source: 90% Federal-NRCS, 5% Lake Restoration, 5% Other, | 2001 East Oak St PO Box 158 | 1850 Hwy 4 South Box 142 | 2721 Sierra Ave | ||||||||||
| Algona IA 50511 | Estherville IA 51334 | Sac City IA 50583 | |||||||||||
| Plan Sets Requested: 0 | Quantities | 515-295-3661 | 712-362-4969 | 712-662-4421 | |||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Mobilization | 1 | L.S. | $3,999.00 | $3,999.00 | $3,000.00 | $3,000.00 | $7,500.00 | $7,500.00 | ||||
| 2 | Excavation | 464 | C.Y. | $5.90 | $2,737.60 | $3.50 | $1,624.00 | $5.50 | $2,552.00 | ||||
| 3 | Earthfill | 14414 | C.Y. | $2.48 | $35,746.72 | $2.00 | $28,828.00 | $3.25 | $46,845.50 | ||||
| 4 | Rip Rap (Class "E") | 60 | Tons | $37.50 | $2,250.00 | $38.00 | $2,280.00 | $58.00 | $3,480.00 | ||||
| 5 | Tile Investigation | 1850 | L.F. | $1.49 | $2,756.50 | $3.00 | $5,550.00 | $2.25 | $4,162.50 | ||||
| 6 | Tile Plugs | 12 | Each | $290.00 | $3,480.00 | $150.00 | $1,800.00 | $325.00 | $3,900.00 | ||||
| 7 | Aluminum Toewall Structure | 1 | Each | $19,484.80 | $19,484.80 | $16,180.00 | $16,180.00 | $19,595.55 | $19,595.55 | ||||
| 8 | 6" P.E. Tubing (non-perf) | 60 | L.F. | $5.30 | $318.00 | $25.00 | $1,500.00 | $10.00 | $600.00 | ||||
| 9 | 10" P.E. Tubing (non perf) | 315 | L.F. | $9.93 | $3,127.95 | $28.00 | $8,820.00 | $12.50 | $3,937.50 | ||||
| 10 | 15" Dual Wall P.E. Tubing (non perf) | 44 | L.F. | $18.84 | $828.96 | $35.00 | $1,540.00 | $25.00 | $1,100.00 | ||||
| 11 | 8" CMP | 20 | L.F. | $14.60 | $292.00 | $15.00 | $300.00 | $22.00 | $440.00 | ||||
| 12 | 12" CMP | 70 | L.F. | $24.94 | $1,745.80 | $25.00 | $1,750.00 | $25.00 | $1,750.00 | ||||
| 13 | 15" CMP | 30 | L.F. | $23.10 | $693.00 | $50.00 | $1,500.00 | $33.00 | $990.00 | ||||
| 14 | 18" CMP | 85 | L.F. | $36.15 | $3,072.75 | $62.00 | $5,270.00 | $60.00 | $5,100.00 | ||||
| 15 | 36" CMP Riser | 1 | Each | $2,711.00 | $2,711.00 | $4,465.00 | $4,465.00 | $5,200.00 | $5,200.00 | ||||
| 16 | Water Control Structure | 1 | Each | $2,310.00 | $2,310.00 | $3,767.00 | $3,767.00 | $4,500.00 | $4,500.00 | ||||
| 17 | Seeding | 6 | Acres | $500.00 | $3,000.00 | $800.00 | $4,800.00 | $850.00 | $5,100.00 | ||||
| 18 | 15" CMP Intake w/12" CMP Pipe | 1 | Each | $819.00 | $819.00 | $1,970.00 | $1,970.00 | $700.00 | $700.00 | ||||
| 19 | Shallow Water Excavation | 1.9 | Acres | $4,842.10 | $9,199.99 | $2,200.00 | $4,180.00 | $1,500.00 | $2,850.00 | ||||
| 20 | Tree Removal | 2.2 | Acres | $4,295.45 | $9,449.99 | $6,400.00 | $14,080.00 | $5,700.00 | $12,540.00 | ||||
| 21 | 10" CMP | 20 | L.F. | $22.25 | $445.00 | $20.00 | $400.00 | $23.50 | $470.00 | ||||
| $108,468.06 | $113,604.00 | $133,313.05 | |||||||||||
4 | 5 | 6 | |||||||||||
| Estimated Cost: $85,500.00 | Contractor: | LeRoy & Sons Inc | |||||||||||
| Funding Source: 90% Federal-NRCS, 5% Lake Restoration, 5% Other, | 405 Dunlap St | ||||||||||||
| Arcadia IA 51430 | |||||||||||||
| Plan Sets Requested: 0 | Quantities | 712-689-2470 | |||||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Mobilization | 1 | L.S. | $12,000.00 | $12,000.00 | $0.00 | $0.00 | ||||||
| 2 | Excavation | 464 | C.Y. | $8.00 | $3,712.00 | $0.00 | $0.00 | ||||||
| 3 | Earthfill | 14414 | C.Y. | $4.00 | $57,656.00 | $0.00 | $0.00 | ||||||
| 4 | Rip Rap (Class "E") | 60 | Tons | $60.00 | $3,600.00 | $0.00 | $0.00 | ||||||
| 5 | Tile Investigation | 1850 | L.F. | $1.40 | $2,590.00 | $0.00 | $0.00 | ||||||
| 6 | Tile Plugs | 12 | Each | $50.00 | $600.00 | $0.00 | $0.00 | ||||||
| 7 | Aluminum Toewall Structure | 1 | Each | $22,000.00 | $22,000.00 | $0.00 | $0.00 | ||||||
| 8 | 6" P.E. Tubing (non-perf) | 60 | L.F. | $8.00 | $480.00 | $0.00 | $0.00 | ||||||
| 9 | 10" P.E. Tubing (non perf) | 315 | L.F. | $15.50 | $4,882.50 | $0.00 | $0.00 | ||||||
| 10 | 15" Dual Wall P.E. Tubing (non perf) | 44 | L.F. | $20.00 | $880.00 | $0.00 | $0.00 | ||||||
| 11 | 8" CMP | 20 | L.F. | $20.00 | $400.00 | $0.00 | $0.00 | ||||||
| 12 | 12" CMP | 70 | L.F. | $25.00 | $1,750.00 | $0.00 | $0.00 | ||||||
| 13 | 15" CMP | 30 | L.F. | $30.00 | $900.00 | $0.00 | $0.00 | ||||||
| 14 | 18" CMP | 85 | L.F. | $35.00 | $2,975.00 | $0.00 | $0.00 | ||||||
| 15 | 36" CMP Riser | 1 | Each | $5,000.00 | $5,000.00 | $0.00 | $0.00 | ||||||
| 16 | Water Control Structure | 1 | Each | $5,000.00 | $5,000.00 | $0.00 | $0.00 | ||||||
| 17 | Seeding | 6 | Acres | $1,200.00 | $7,200.00 | $0.00 | $0.00 | ||||||
| 18 | 15" CMP Intake w/12" CMP Pipe | 1 | Each | $4,000.00 | $4,000.00 | $0.00 | $0.00 | ||||||
| 19 | Shallow Water Excavation | 1.9 | Acres | $4,000.00 | $7,600.00 | $0.00 | $0.00 | ||||||
| 20 | Tree Removal | 2.2 | Acres | $6,000.00 | $13,200.00 | $0.00 | $0.00 | ||||||
| 21 | 10" CMP | 20 | L.F. | $25.00 | $500.00 | $0.00 | $0.00 | ||||||
| $156,925.50 | $0.00 | $0.00 | |||||||||||