IOWA DEPARTMENT OF NATURAL RESOURCES |
|
| Bids For: | Location: | Ledges State Park | Date: 1/20/2011 | Project No. |
| Debris & Sediment Removal FHWA - Sites 3 and 4 | County: | BOONE | Time: 3:00 p.m. | 11-02-08-08 |
1 | 2 | 3 | |||||||||||
| Estimated Cost: $25,000.00 | Contractor: | STONY CREEK LANDSCAPES | Burr Oak Springs Limited | Schoon Construction Inc | |||||||||
| Funding Source: 100% Federal-Other, | 404 E 2nd St | 2113 County Rd W-14 | 1500 S 2nd St | ||||||||||
| Webster City IA 50595 | Ridgeway IA 52165 | Cherokee IA 51012 | |||||||||||
| Plan Sets Requested: 0 | Quantities | 515-832-1281 | 563-737-3510 | 712-225-5736 | |||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Excavation - Fill | 400 | C.Y. | $8.14 | $3,256.00 | $20.00 | $8,000.00 | $20.00 | $8,000.00 | ||||
| 2 | Granular Shoulders | 100 | Tons | $36.15 | $3,615.00 | $20.00 | $2,000.00 | $40.00 | $4,000.00 | ||||
| 3 | Permanent Erosion Control | 1 | L.S. | $1,965.00 | $1,965.00 | $3,000.00 | $3,000.00 | $3,852.00 | $3,852.00 | ||||
| 4 | Reshaping Ditch | 4 | STA. | $1,427.50 | $5,710.00 | $400.00 | $1,600.00 | $1,250.00 | $5,000.00 | ||||
| 5 | Clean Pipe Culverts | 259 | L.F. | $13.73 | $3,556.07 | $20.00 | $5,180.00 | $30.00 | $7,770.00 | ||||
| $18,102.07 | $19,780.00 | $28,622.00 | |||||||||||
4 | 5 | 6 | |||||||||||
| Estimated Cost: $25,000.00 | Contractor: | HEALY EXCAVATING | Richards Construction Co Inc | ||||||||||
| Funding Source: 100% Federal-Other, | 3483 Perkins Ave | 2721 Sierra Ave | |||||||||||
| Lake View IA 51450 | Sac City IA 50583 | ||||||||||||
| Plan Sets Requested: 0 | Quantities | 712-665-4500 | 712-662-4421 | ||||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Excavation - Fill | 400 | C.Y. | $4.00 | $1,600.00 | $12.00 | $4,800.00 | $0.00 | |||||
| 2 | Granular Shoulders | 100 | Tons | $37.50 | $3,750.00 | $42.00 | $4,200.00 | $0.00 | |||||
| 3 | Permanent Erosion Control | 1 | L.S. | $7,500.00 | $7,500.00 | $6,000.00 | $6,000.00 | $0.00 | |||||
| 4 | Reshaping Ditch | 4 | STA. | $3,875.00 | $15,500.00 | $2,200.00 | $8,800.00 | $0.00 | |||||
| 5 | Clean Pipe Culverts | 259 | L.F. | $14.50 | $3,755.50 | $40.00 | $10,360.00 | $0.00 | |||||
| $32,105.50 | $34,160.00 | $0.00 | |||||||||||
10/13/2026