| Bids For: | Location: | Mt. Ayr | Date: 5/26/2011 | Project No. |
| We have a road culvert washing | County: | RINGGOLD | Time: 3:00 p.m. | 10-04-80-02 |
1 | 2 | 3 | |||||||||||
| Estimated Cost: $2,500.00 | Contractor: | TEK Builders, Inc. | Godby Land Improvements | Schaefer Excavating Inc | |||||||||
| Funding Source: 75% Federal-FEMA 1, 25% F&W Trust - Other, | 201 N Taylor PO Box 632 | 2569 - 560th Ave | 1864 215th Street | ||||||||||
| Mount Ayr IA 50854 | Albia IA 52531 | Mt Ayr IA 50854 | |||||||||||
| Plan Sets Requested: 0 | Quantities | 641-464-3972 | 641-895-0505 | 641-464-2419 | |||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Resetting Culvert | 1 | L.S. | $448.00 | $448.00 | $800.00 | $800.00 | $1,040.00 | $1,040.00 | ||||
| 2 | Site Grading | 1 | L.S. | $900.00 | $900.00 | $750.00 | $750.00 | $650.00 | $650.00 | ||||
| 3 | Site Restoration | 1 | L.S. | $100.00 | $100.00 | $250.00 | $250.00 | $850.00 | $850.00 | ||||
| $1,448.00 | $1,800.00 | $2,540.00 | |||||||||||
4 | 5 | 6 | |||||||||||
| Estimated Cost: $2,500.00 | Contractor: | Jeff Sickels Dozing LLC | |||||||||||
| Funding Source: 75% Federal-FEMA 1, 25% F&W Trust - Other, | 2047 - 220th St | ||||||||||||
| Mount Ayr IA 50854 | |||||||||||||
| Plan Sets Requested: 0 | Quantities | 641-464-2453 | |||||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Resetting Culvert | 1 | L.S. | $1,500.00 | $1,500.00 | $0.00 | $0.00 | ||||||
| 2 | Site Grading | 1 | L.S. | $1,000.00 | $1,000.00 | $0.00 | $0.00 | ||||||
| 3 | Site Restoration | 1 | L.S. | $750.00 | $750.00 | $0.00 | $0.00 | ||||||
| $3,250.00 | $0.00 | $0.00 | |||||||||||