IOWA DEPARTMENT OF NATURAL RESOURCES
ENGINEERING BUREAU

INFORMAL BID TAB
NOTICE: This document represents bids that were opened on the letting date and may be subject to further review. This is not the official bid tab.

 Bids For:  Location:   Lake Darling  Date: 6/23/2011  Project No.  
  Low Water Crossing  County:   WASHINGTON  Time: 3:00 p.m.  11-06-92-03

 

 
1
2
3
Estimated Cost:
Contractor: 
James Waterhouse Construction
Funding Source: 100% Lake Restoration, 1235 Hoot Owl Hollow


Keota IA  52248    
Plan Sets Requested: 0
Quantities
319-698-2102
No.Description:No.UnitUnit Price AmountUnit Price AmountUnit Price Amount
1MOBILIZATION1L.S.$3,000.00$3,000.00 $0.00 $0.00 
2CLEARING AND GRUBBING1L.S.$4,000.00$4,000.00 $0.00 $0.00 
3EXCAVATION250C.Y.$30.00$7,500.00 $0.00 $0.00 
4FENCE1L.S.$3,000.00$3,000.00 $0.00 $0.00 
5CONCRETE 6"1374S.F.$10.78$14,811.72 $0.00 $0.00 
6MACADAM STONE91Tons$27.00$2,457.00 $0.00 $0.00 
7ENGINEERED FABRIC1950S.F.$1.03$2,008.50 $0.00 $0.00 
818" CULVERT54L.F.$48.15$2,600.10 $0.00 $0.00 
9CLASS A CRUSHED STONE223Tons$28.50$6,355.50 $0.00 $0.00 
10SITE RESTORATION1L.S.$3,000.00$3,000.00 $0.00 $0.00 
      $48,732.82  $0.00  $0.00 
 



 