| Bids For: | Location: | Saylorville Wildlife Unit | Date: 6/16/2011 | Project No. |
| Headquarters Building | County: | BOONE | Time: 11:00 a.m. | 11-02-08-01 |
1 | 2 | 3 | |||||||||||
| Estimated Cost: $275,000.00 | Contractor: | R H Grabau Construction Inc | Joiner Construction Co. Inc. | ||||||||||
| Funding Source: 24% REAP Land Management, 70% Federal-PR, 3% F&W Trust-Fisheries Non-Habitat Stamp, 3% Marine Fuel Tax | 871 "P" Ave PO Box | 11996 490th St | |||||||||||
| Boone IA 50036 | Plano IA 52581 | ||||||||||||
| Plan Sets Requested: 5 | Quantities | (515) 432-6935 | 641-649-2646 | ||||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Pre-Engineered Building, Complete | 1 | L.S. | $180,814.00 | $180,814.00 | $165,000.00 | $165,000.00 | $0.00 | |||||
| 2 | Excavation, On Site Borrow | 180 | C.Y. | $42.22 | $7,599.60 | $58.06 | $10,450.80 | $0.00 | |||||
| 3 | Concrete, Interior Slab, 6" | 4120 | S.F. | $6.45 | $26,574.00 | $7.79 | $32,094.80 | $0.00 | |||||
| 4 | Concrete, Exterior Apron, 6" | 3000 | S.F. | $6.00 | $18,000.00 | $6.00 | $18,000.00 | $0.00 | |||||
| 5 | Base, Cl. "A" Cr. Stone | 140 | Tons | $21.42 | $2,998.80 | $25.00 | $3,500.00 | $0.00 | |||||
| 6 | Electrical Service/System, 120/240V, Complete | 1 | L.S. | $25,000.00 | $25,000.00 | $27,000.00 | $27,000.00 | $0.00 | |||||
| 7 | HVAC System, Complete (Including LP Gas Service) | 1 | L.S. | $17,000.00 | $17,000.00 | $26,000.00 | $26,000.00 | $0.00 | |||||
| 8 | Water System, Complete As Per Plan | 1 | L.S. | $9,000.00 | $9,000.00 | $30,000.00 | $30,000.00 | $0.00 | |||||
| 9 | Septic System, Complete As Per Plan | 1 | L.S. | $26,000.00 | $26,000.00 | $15,000.00 | $15,000.00 | $0.00 | |||||
| 10 | Seeding, Fertilizing & Mulching | 1 | L.S. | $345.00 | $345.00 | $4,000.00 | $4,000.00 | $0.00 | |||||
| $313,331.40 | $331,045.60 | $0.00 | |||||||||||
10/13/2026