 Bids For:  Location:   Saylorville Wildlife Unit  Date: 6/16/2011  Project No.  
  Headquarters Building  County:   BOONE  Time: 11:00 a.m.  11-02-08-01

 

 
1
2
3
Estimated Cost: $275,000.00
Contractor: 
R H Grabau Construction IncJoiner Construction Co. Inc.
Funding Source: 24% REAP Land Management, 70% Federal-PR, 3% F&W Trust-Fisheries Non-Habitat Stamp, 3% Marine Fuel Tax871 "P" Ave
PO Box
11996 490th St

Boone IA  50036Plano IA  52581  
Plan Sets Requested: 5
Quantities
(515) 432-6935641-649-2646
No.Description:No.UnitUnit Price AmountUnit Price AmountUnit Price Amount
1Pre-Engineered Building, Complete1L.S.$180,814.00$180,814.00 $165,000.00$165,000.00 $0.00 
2Excavation, On Site Borrow180C.Y.$42.22$7,599.60 $58.06$10,450.80 $0.00 
3Concrete, Interior Slab, 6"4120S.F.$6.45$26,574.00 $7.79$32,094.80 $0.00 
4Concrete, Exterior Apron, 6"3000S.F.$6.00$18,000.00 $6.00$18,000.00 $0.00 
5Base, Cl. "A" Cr. Stone140Tons$21.42$2,998.80 $25.00$3,500.00 $0.00 
6Electrical Service/System, 120/240V, Complete1L.S.$25,000.00$25,000.00 $27,000.00$27,000.00 $0.00 
7HVAC System, Complete (Including LP Gas Service)1L.S.$17,000.00$17,000.00 $26,000.00$26,000.00 $0.00 
8Water System, Complete As Per Plan1L.S.$9,000.00$9,000.00 $30,000.00$30,000.00 $0.00 
9Septic System, Complete As Per Plan1L.S.$26,000.00$26,000.00 $15,000.00$15,000.00 $0.00 
10Seeding, Fertilizing & Mulching1L.S.$345.00$345.00 $4,000.00$4,000.00 $0.00 
      $313,331.40  $331,045.60  $0.00 
 



 