IOWA DEPARTMENT OF NATURAL RESOURCES
ENGINEERING BUREAU

INFORMAL BID TAB
NOTICE: This document represents bids that were opened on the letting date and may be subject to further review. This is not the official bid tab.

 Bids For:  Location:   Backbone State Park  Date: 5/10/2011  Project No.  
  Flood clean up contract  County:   DELAWARE  Time: 3:00 p.m.  11-03-28-07

 

 
1
2
3
Estimated Cost: $90,000.00
Contractor: 
Riehm Construction CompanyLANSING BROTHERS CONSTRUCTIONEastern Iowa Excavating & Concrete LLC
Funding Source: 90% Federal-FEMA 1, 10% Executive Council, 2340 - 9th St SW
PO Box 36
121 Nixon St SE
PO Box 189
Waukon IA  52172Luxemburg IA  52056Cascade IA  52033
Plan Sets Requested: 0
Quantities
563-568-3314563-853-2645563-852-5120
No.Description:No.UnitUnit Price AmountUnit Price AmountUnit Price Amount
1Mobilization1L.S.$9,500.00$9,500.00 $3,800.00$3,800.00 $3,500.00$3,500.00 
2Traffic Control7Day$190.00$1,330.00 $80.00$560.00 $142.86$1,000.02 
3Seeding2Acres$1,000.00$2,000.00 $2,500.00$5,000.00 $1,950.00$3,900.00 
4Silt Removal4490C.Y.$3.50$15,715.00 $5.50$24,695.00 $7.50$33,675.00 
5Debris Removal391C.Y.$6.50$2,541.50 $10.00$3,910.00 $21.00$8,211.00 
6Tree Removal82.5Units$18.75$1,546.875 $20.00$1,650.00 $45.00$3,712.50 
7Sand Removal185C.Y.$15.00$2,775.00 $10.00$1,850.00 $12.00$2,220.00 
8Revetment, Class 'D'58Tons$25.00$1,450.00 $25.00$1,450.00 $28.00$1,624.00 
9Mason Sand260Tons$16.25$4,225.00 $15.00$3,900.00 $17.50$4,550.00 
10Earth Fill, Contractor Furnished700C.Y.$8.50$5,950.00 $8.00$5,600.00 $16.50$11,550.00 
11Roadstone 3" Cr. Stone Base350Tons$13.00$4,550.00 $13.00$4,550.00 $14.25$4,987.50 
12Surfacing, 3/4" Cr. Stone560Tons$13.00$7,280.00 $13.00$7,280.00 $14.25$7,980.00 
13Sidewalk Removal34S.Y.$40.00$1,360.00 $10.00$340.00 $5.00$170.00 
14Sidewalk, 4" PC Concrete34S.Y.$100.00$3,400.00 $40.00$1,360.00 $30.00$1,020.00 
      $63,623.375  $65,945.00  $88,100.02 
 
 
4
5
6
Estimated Cost: $90,000.00
Contractor: 
Tschigffrie Excavating CoSteger Construction IncCJ Moyna & Sons Inc
Funding Source: 90% Federal-FEMA 1, 10% Executive Council, 425 Julian Dubuque Dr
PO Box 3280
3297 Vine Rd
24412 Hwy 13
Dubuque IA  52003Dyersville IA  52040Elkader IA  52043
Plan Sets Requested: 0
Quantities
563-557-7450563-875-7876563-245-1442
No.Description:No.UnitUnit Price AmountUnit Price AmountUnit Price Amount
1Mobilization1L.S.$5,472.75$5,472.75 $3,000.00$3,000.00 $20,000.00$20,000.00 
2Traffic Control7Day$366.65$2,566.55 $600.00$4,200.00 $800.00$5,600.00 
3Seeding2Acres$2,000.00$4,000.00 $1,800.00$3,600.00 $3,000.00$6,000.00 
4Silt Removal4490C.Y.$8.90$39,961.00 $10.00$44,900.00 $12.00$53,880.00 
5Debris Removal391C.Y.$9.05$3,538.55 $25.00$9,775.00 $40.00$15,640.00 
6Tree Removal82.5Units$15.00$1,237.50 $18.00$1,485.00 $50.00$4,125.00 
7Sand Removal185C.Y.$11.70$2,164.50 $12.00$2,220.00 $30.00$5,550.00 
8Revetment, Class 'D'58Tons$27.55$1,597.90 $24.40$1,415.20 $56.00$3,248.00 
9Mason Sand260Tons$13.35$3,471.00 $14.75$3,835.00 $24.00$6,240.00 
10Earth Fill, Contractor Furnished700C.Y.$21.40$14,980.00 $10.00$7,000.00 $14.00$9,800.00 
11Roadstone 3" Cr. Stone Base350Tons$13.50$4,725.00 $14.25$4,987.50 $17.00$5,950.00 
12Surfacing, 3/4" Cr. Stone560Tons$13.55$7,588.00 $14.25$7,980.00 $18.00$10,080.00 
13Sidewalk Removal34S.Y.$12.00$408.00 $10.00$340.00 $30.00$1,020.00 
14Sidewalk, 4" PC Concrete34S.Y.$68.50$2,329.00 $40.50$1,377.00 $100.00$3,400.00 
      $94,039.75  $96,114.70  $150,533.00 
 
7
8
9
Estimated Cost: $90,000.00
Contractor: 
Baker Concrete & Excavating
Funding Source: 90% Federal-FEMA 1, 10% Executive Council, 2203 E. Bremer Ave


Waverly IA  50677    
Plan Sets Requested: 0
Quantities
319-352-2193
No.Description:No.UnitUnit Price AmountUnit Price AmountUnit Price Amount
1Mobilization1L.S.$11,500.00$11,500.00 $0.00 $0.00 
2Traffic Control7Day$500.00$3,500.00 $0.00 $0.00 
3Seeding2Acres$2,500.00$5,000.00 $0.00 $0.00 
4Silt Removal4490C.Y.$14.80$66,452.00 $0.00 $0.00 
5Debris Removal391C.Y.$37.80$14,779.80 $0.00 $0.00 
6Tree Removal82.5Units$39.50$3,258.75 $0.00 $0.00 
7Sand Removal185C.Y.$14.50$2,682.50 $0.00 $0.00 
8Revetment, Class 'D'58Tons$38.00$2,204.00 $0.00 $0.00 
9Mason Sand260Tons$15.80$4,108.00 $0.00 $0.00 
10Earth Fill, Contractor Furnished700C.Y.$29.60$20,720.00 $0.00 $0.00 
11Roadstone 3" Cr. Stone Base350Tons$19.60$6,860.00 $0.00 $0.00 
12Surfacing, 3/4" Cr. Stone560Tons$19.75$11,060.00 $0.00 $0.00 
13Sidewalk Removal34S.Y.$18.85$640.90 $0.00 $0.00 
14Sidewalk, 4" PC Concrete34S.Y.$42.60$1,448.40 $0.00 $0.00 
      $154,214.35  $0.00  $0.00 
 



 

10/13/2026