IOWA DEPARTMENT OF NATURAL RESOURCES |
|
| Bids For: | Location: | Backbone State Park | Date: 5/10/2011 | Project No. |
| Flood clean up contract | County: | DELAWARE | Time: 3:00 p.m. | 11-03-28-07 |
1 | 2 | 3 | |||||||||||
| Estimated Cost: $90,000.00 | Contractor: | Riehm Construction Company | LANSING BROTHERS CONSTRUCTION | Eastern Iowa Excavating & Concrete LLC | |||||||||
| Funding Source: 90% Federal-FEMA 1, 10% Executive Council, | 2340 - 9th St SW | PO Box 36 | 121 Nixon St SE PO Box 189 | ||||||||||
| Waukon IA 52172 | Luxemburg IA 52056 | Cascade IA 52033 | |||||||||||
| Plan Sets Requested: 0 | Quantities | 563-568-3314 | 563-853-2645 | 563-852-5120 | |||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Mobilization | 1 | L.S. | $9,500.00 | $9,500.00 | $3,800.00 | $3,800.00 | $3,500.00 | $3,500.00 | ||||
| 2 | Traffic Control | 7 | Day | $190.00 | $1,330.00 | $80.00 | $560.00 | $142.86 | $1,000.02 | ||||
| 3 | Seeding | 2 | Acres | $1,000.00 | $2,000.00 | $2,500.00 | $5,000.00 | $1,950.00 | $3,900.00 | ||||
| 4 | Silt Removal | 4490 | C.Y. | $3.50 | $15,715.00 | $5.50 | $24,695.00 | $7.50 | $33,675.00 | ||||
| 5 | Debris Removal | 391 | C.Y. | $6.50 | $2,541.50 | $10.00 | $3,910.00 | $21.00 | $8,211.00 | ||||
| 6 | Tree Removal | 82.5 | Units | $18.75 | $1,546.875 | $20.00 | $1,650.00 | $45.00 | $3,712.50 | ||||
| 7 | Sand Removal | 185 | C.Y. | $15.00 | $2,775.00 | $10.00 | $1,850.00 | $12.00 | $2,220.00 | ||||
| 8 | Revetment, Class 'D' | 58 | Tons | $25.00 | $1,450.00 | $25.00 | $1,450.00 | $28.00 | $1,624.00 | ||||
| 9 | Mason Sand | 260 | Tons | $16.25 | $4,225.00 | $15.00 | $3,900.00 | $17.50 | $4,550.00 | ||||
| 10 | Earth Fill, Contractor Furnished | 700 | C.Y. | $8.50 | $5,950.00 | $8.00 | $5,600.00 | $16.50 | $11,550.00 | ||||
| 11 | Roadstone 3" Cr. Stone Base | 350 | Tons | $13.00 | $4,550.00 | $13.00 | $4,550.00 | $14.25 | $4,987.50 | ||||
| 12 | Surfacing, 3/4" Cr. Stone | 560 | Tons | $13.00 | $7,280.00 | $13.00 | $7,280.00 | $14.25 | $7,980.00 | ||||
| 13 | Sidewalk Removal | 34 | S.Y. | $40.00 | $1,360.00 | $10.00 | $340.00 | $5.00 | $170.00 | ||||
| 14 | Sidewalk, 4" PC Concrete | 34 | S.Y. | $100.00 | $3,400.00 | $40.00 | $1,360.00 | $30.00 | $1,020.00 | ||||
| $63,623.375 | $65,945.00 | $88,100.02 | |||||||||||
4 | 5 | 6 | |||||||||||
| Estimated Cost: $90,000.00 | Contractor: | Tschigffrie Excavating Co | Steger Construction Inc | CJ Moyna & Sons Inc | |||||||||
| Funding Source: 90% Federal-FEMA 1, 10% Executive Council, | 425 Julian Dubuque Dr PO Box 3280 | 3297 Vine Rd | 24412 Hwy 13 | ||||||||||
| Dubuque IA 52003 | Dyersville IA 52040 | Elkader IA 52043 | |||||||||||
| Plan Sets Requested: 0 | Quantities | 563-557-7450 | 563-875-7876 | 563-245-1442 | |||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Mobilization | 1 | L.S. | $5,472.75 | $5,472.75 | $3,000.00 | $3,000.00 | $20,000.00 | $20,000.00 | ||||
| 2 | Traffic Control | 7 | Day | $366.65 | $2,566.55 | $600.00 | $4,200.00 | $800.00 | $5,600.00 | ||||
| 3 | Seeding | 2 | Acres | $2,000.00 | $4,000.00 | $1,800.00 | $3,600.00 | $3,000.00 | $6,000.00 | ||||
| 4 | Silt Removal | 4490 | C.Y. | $8.90 | $39,961.00 | $10.00 | $44,900.00 | $12.00 | $53,880.00 | ||||
| 5 | Debris Removal | 391 | C.Y. | $9.05 | $3,538.55 | $25.00 | $9,775.00 | $40.00 | $15,640.00 | ||||
| 6 | Tree Removal | 82.5 | Units | $15.00 | $1,237.50 | $18.00 | $1,485.00 | $50.00 | $4,125.00 | ||||
| 7 | Sand Removal | 185 | C.Y. | $11.70 | $2,164.50 | $12.00 | $2,220.00 | $30.00 | $5,550.00 | ||||
| 8 | Revetment, Class 'D' | 58 | Tons | $27.55 | $1,597.90 | $24.40 | $1,415.20 | $56.00 | $3,248.00 | ||||
| 9 | Mason Sand | 260 | Tons | $13.35 | $3,471.00 | $14.75 | $3,835.00 | $24.00 | $6,240.00 | ||||
| 10 | Earth Fill, Contractor Furnished | 700 | C.Y. | $21.40 | $14,980.00 | $10.00 | $7,000.00 | $14.00 | $9,800.00 | ||||
| 11 | Roadstone 3" Cr. Stone Base | 350 | Tons | $13.50 | $4,725.00 | $14.25 | $4,987.50 | $17.00 | $5,950.00 | ||||
| 12 | Surfacing, 3/4" Cr. Stone | 560 | Tons | $13.55 | $7,588.00 | $14.25 | $7,980.00 | $18.00 | $10,080.00 | ||||
| 13 | Sidewalk Removal | 34 | S.Y. | $12.00 | $408.00 | $10.00 | $340.00 | $30.00 | $1,020.00 | ||||
| 14 | Sidewalk, 4" PC Concrete | 34 | S.Y. | $68.50 | $2,329.00 | $40.50 | $1,377.00 | $100.00 | $3,400.00 | ||||
| $94,039.75 | $96,114.70 | $150,533.00 | |||||||||||
7 | 8 | 9 | |||||||||||
| Estimated Cost: $90,000.00 | Contractor: | Baker Concrete & Excavating | |||||||||||
| Funding Source: 90% Federal-FEMA 1, 10% Executive Council, | 2203 E. Bremer Ave | ||||||||||||
| Waverly IA 50677 | |||||||||||||
| Plan Sets Requested: 0 | Quantities | 319-352-2193 | |||||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Mobilization | 1 | L.S. | $11,500.00 | $11,500.00 | $0.00 | $0.00 | ||||||
| 2 | Traffic Control | 7 | Day | $500.00 | $3,500.00 | $0.00 | $0.00 | ||||||
| 3 | Seeding | 2 | Acres | $2,500.00 | $5,000.00 | $0.00 | $0.00 | ||||||
| 4 | Silt Removal | 4490 | C.Y. | $14.80 | $66,452.00 | $0.00 | $0.00 | ||||||
| 5 | Debris Removal | 391 | C.Y. | $37.80 | $14,779.80 | $0.00 | $0.00 | ||||||
| 6 | Tree Removal | 82.5 | Units | $39.50 | $3,258.75 | $0.00 | $0.00 | ||||||
| 7 | Sand Removal | 185 | C.Y. | $14.50 | $2,682.50 | $0.00 | $0.00 | ||||||
| 8 | Revetment, Class 'D' | 58 | Tons | $38.00 | $2,204.00 | $0.00 | $0.00 | ||||||
| 9 | Mason Sand | 260 | Tons | $15.80 | $4,108.00 | $0.00 | $0.00 | ||||||
| 10 | Earth Fill, Contractor Furnished | 700 | C.Y. | $29.60 | $20,720.00 | $0.00 | $0.00 | ||||||
| 11 | Roadstone 3" Cr. Stone Base | 350 | Tons | $19.60 | $6,860.00 | $0.00 | $0.00 | ||||||
| 12 | Surfacing, 3/4" Cr. Stone | 560 | Tons | $19.75 | $11,060.00 | $0.00 | $0.00 | ||||||
| 13 | Sidewalk Removal | 34 | S.Y. | $18.85 | $640.90 | $0.00 | $0.00 | ||||||
| 14 | Sidewalk, 4" PC Concrete | 34 | S.Y. | $42.60 | $1,448.40 | $0.00 | $0.00 | ||||||
| $154,214.35 | $0.00 | $0.00 | |||||||||||