 Bids For:  Location:   Stone State park  Date: 3/15/2012  Project No.  
  Slope Failure  County:   WOODBURY  Time: 11:00 a.m.  11-01-75-02

 

 
1
2
3
Estimated Cost: $92,000.00
Contractor: 
Nelson & Rock ContractingK & L Landscape & Construction IncL.A. Carlson Contracting, Inc.
Funding Source: 100% Park & Institutional Road Fund, 23565 Hwy K45
501 S Ridge Rd
20984 C-43
Onawa IA  51040Sergeant Bluff IA  51054Merrill IA  51038
Plan Sets Requested: 6
Quantities
7124231065712-943-2939712-239-3195
No.Description:No.UnitUnit Price AmountUnit Price AmountUnit Price Amount
1Mobilization1L.S.$8,000.00$8,000.00 $7,500.00$7,500.00 $10,000.00$10,000.00 
2Clearing & Grubbing0.5Acres$7,000.00$3,500.00 $2,000.00$1,000.00 $30,000.00$15,000.00 
3Excavation Class 241700C.Y.$8.00$13,600.00 $8.00$13,600.00 $15.00$25,500.00 
4Excavation Class 101000C.Y.$3.00$3,000.00 $10.00$10,000.00 $6.50$6,500.00 
5Granular Material200Tons$31.00$6,200.00 $25.00$5,000.00 $39.50$7,900.00 
6Modified Subbase175Tons$26.00$4,550.00 $25.00$4,375.00 $28.50$4,987.50 
7Hot Mix Asphalt140Tons$110.00$15,400.00 $112.00$15,680.00 $100.00$14,000.00 
8Reconstruction of Road Bed800C.Y.$3.00$2,400.00 $6.00$4,800.00 $8.50$6,800.00 
9Removal of Existing Structures1L.S.$2,000.00$2,000.00 $1,500.00$1,500.00 $2,500.00$2,500.00 
10Aprons, Concrete 48 in. Dia.1Each$3,500.00$3,500.00 $3,500.00$3,500.00 $4,000.00$4,000.00 
11Culvert, Unclassified Entrance Pipe 48" Dia.192L.F.$130.00$24,960.00 $190.00$36,480.00 $150.00$28,800.00 
12Manhole, Storm Sewer SW-4031Each$7,000.00$7,000.00 $9,500.00$9,500.00 $8,500.00$8,500.00 
13Engineering Fabric600S.Y.$3.00$1,800.00 $3.00$1,800.00 $2.50$1,500.00 
14Removal of Pavement130Tons$30.00$3,900.00 $10.00$1,300.00 $17.00$2,210.00 
15Traffic Control1L.S.$1,000.00$1,000.00 $750.00$750.00 $1,500.00$1,500.00 
16Fertilizing1Acres$500.00$500.00 $500.00$500.00 $275.00$275.00 
17Mulching1Acres$700.00$700.00 $3,750.00$3,750.00 $1,155.00$1,155.00 
18Native Grass Seeding1Acres$2,500.00$2,500.00 $2,500.00$2,500.00 $1,705.00$1,705.00 
19Turf Reinforcement Mat60S.Y.$40.00$2,400.00 $32.00$1,920.00 $51.15$3,069.00 
20Silt Fence240L.F.$2.00$480.00 $4.00$960.00 $7.70$1,848.00 
      $107,390.00  $126,415.00  $147,749.50 
 
4
5
6
Estimated Cost: $92,000.00
Contractor: 
Lessard Contracting Inc
Funding Source: 100% Park & Institutional Road Fund, PO Box 705


Sergeant Bluff IA  51054-0705    
Plan Sets Requested: 6
Quantities
712-252-4131
No.Description:No.UnitUnit Price AmountUnit Price AmountUnit Price Amount
1Mobilization1L.S.$19,601.00$19,601.00 $0.00 $0.00 
2Clearing & Grubbing0.5Acres$23,000.00$11,500.00 $0.00 $0.00 
3Excavation Class 241700C.Y.$13.65$23,205.00 $0.00 $0.00 
4Excavation Class 101000C.Y.$7.35$7,350.00 $0.00 $0.00 
5Granular Material200Tons$37.00$7,400.00 $0.00 $0.00 
6Modified Subbase175Tons$34.00$5,950.00 $0.00 $0.00 
7Hot Mix Asphalt140Tons$92.00$12,880.00 $0.00 $0.00 
8Reconstruction of Road Bed800C.Y.$5.85$4,680.00 $0.00 $0.00 
9Removal of Existing Structures1L.S.$2,500.00$2,500.00 $0.00 $0.00 
10Aprons, Concrete 48 in. Dia.1Each$3,850.00$3,850.00 $0.00 $0.00 
11Culvert, Unclassified Entrance Pipe 48" Dia.192L.F.$155.00$29,760.00 $0.00 $0.00 
12Manhole, Storm Sewer SW-4031Each$9,450.00$9,450.00 $0.00 $0.00 
13Engineering Fabric600S.Y.$3.00$1,800.00 $0.00 $0.00 
14Removal of Pavement130Tons$28.00$3,640.00 $0.00 $0.00 
15Traffic Control1L.S.$1,555.00$1,555.00 $0.00 $0.00 
16Fertilizing1Acres$250.00$250.00 $0.00 $0.00 
17Mulching1Acres$800.00$800.00 $0.00 $0.00 
18Native Grass Seeding1Acres$3,100.00$3,100.00 $0.00 $0.00 
19Turf Reinforcement Mat60S.Y.$16.00$960.00 $0.00 $0.00 
20Silt Fence240L.F.$4.00$960.00 $0.00 $0.00 
      $151,191.00  $0.00  $0.00 
 



 