 Bids For:  Location:   Palisades Kepler State Park  Date: 3/24/2011  Project No.  
  Replace lodge roof  County:   LINN  Time: 3:00 p.m.  11-06-57-02

 

 
1
2
3
Estimated Cost: $38,460.00
Contractor: 
Vieco Dev. & Construction Co. Inc.
Funding Source: 100% REAP Land Management, 3 Victorian Ct
PO Box 8022


Saint Joseph MO  64507    
Plan Sets Requested: 0
Quantities
816-232-9044
No.Description:No.UnitUnit Price AmountUnit Price AmountUnit Price Amount
1Shingle Removal50SQ.$110.00$5,500.00 $0.00 $0.00 
2Shingle Replacement50SQ.$770.00$38,500.00 $0.00 $0.00 
3Ridge Cap266L.F.$5.00$1,330.00 $0.00 $0.00 
4Roofline Repairs5Each$400.00$2,000.00 $0.00 $0.00 
5Replace Damaged Sheathing32S.F.$10.00$320.00 $0.00 $0.00 
      $47,650.00  $0.00  $0.00 
 



 