 Bids For:  Location:   Lakin Slough  Date: 4/14/2011  Project No.  
  Installation of fish barrier  County:   GUTHRIE  Time: 3:00 p.m.  11-04-39-01

 

 
1
2
3
Estimated Cost: $39,500.00
Contractor: 
Richards Construction Co Inc
Funding Source: 100% F&W Trust-Wildlife Non-Habitat Stamp, 2721 Sierra Ave


Sac City IA  50583    
Plan Sets Requested: 0
Quantities
712-662-4421
No.Description:No.UnitUnit Price AmountUnit Price AmountUnit Price Amount
1Site Work1L.S.$5,778.08$5,778.08 $0.00 $0.00 
2Provide & Install Fish Barrier Structure1L.S.$14,500.00$14,500.00 $0.00 $0.00 
3Aluminum Fish Barrier Screens9Each$255.00$2,295.00 $0.00 $0.00 
4Stop Log Storage Rack1Each$1,750.00$1,750.00 $0.00 $0.00 
5Aluminum Fish Grates3Each$1,850.00$5,550.00 $0.00 $0.00 
      $29,873.08  $0.00  $0.00 
 



 