IOWA DEPARTMENT OF NATURAL RESOURCES |
|
| Bids For: | Location: | Manchester Fish Hatchery | Date: 9/23/2010 | Project No. |
| Roofing Project | County: | DELAWARE | Time: 3:00 p.m. | 11-03-28-02 |
1 | 2 | 3 | |||||||||||
| Estimated Cost: $25,000.00 | Contractor: | Matt Construction Inc | NEUHAUS CONSTRUCTION & CONCRETE | Porter & Porter Construction LLC | |||||||||
| Funding Source: 75% Federal-DJ, 25% REAP Land Management, | 203 Y Ave | 2259 Jefferson Rd | 1728 Grant Avenue | ||||||||||
| Sumner IA 50674 | MANCHESTER IA 52057 | Independence IA 50644 | |||||||||||
| Plan Sets Requested: 0 | Quantities | 563-578-8418 | 563-927-5178 | 319-334-4861 | |||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Mobilization | 1 | L.S. | $1,500.00 | $1,500.00 | $125.00 | $125.00 | $1,810.00 | $1,810.00 | ||||
| 2 | Furnish & Place Metal Roof On Hatchery Shop | 1 | L.S. | $5,162.00 | $5,162.00 | $6,631.67 | $6,631.67 | $5,950.00 | $5,950.00 | ||||
| 3 | Furnish & Place Metal Roof On Feed Storage Building | 1 | L.S. | $5,700.00 | $5,700.00 | $7,934.93 | $7,934.93 | $7,140.00 | $7,140.00 | ||||
| 4 | Furnish & Place Metal Roof On Oil Storage Building | 1 | L.S. | $1,200.00 | $1,200.00 | $1,628.46 | $1,628.46 | $980.00 | $980.00 | ||||
| 5 | Replace Gutter System On Hatchery Shop | 1 | L.S. | $500.00 | $500.00 | $269.64 | $269.64 | $835.00 | $835.00 | ||||
| $14,062.00 | $16,589.70 | $16,715.00 | |||||||||||
4 | 5 | 6 | |||||||||||
| Estimated Cost: $25,000.00 | Contractor: | Champz Construction | Hanson Construction LLC | ||||||||||
| Funding Source: 75% Federal-DJ, 25% REAP Land Management, | PO Box 267 | PO Box 614 | |||||||||||
| Lawler IA 52154 | Clear Lake IA 50428 | ||||||||||||
| Plan Sets Requested: 0 | Quantities | 563-357-1521 | 641-357-8171 | ||||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Mobilization | 1 | L.S. | $1,500.00 | $1,500.00 | $3,000.00 | $3,000.00 | $0.00 | |||||
| 2 | Furnish & Place Metal Roof On Hatchery Shop | 1 | L.S. | $6,300.00 | $6,300.00 | $9,500.00 | $9,500.00 | $0.00 | |||||
| 3 | Furnish & Place Metal Roof On Feed Storage Building | 1 | L.S. | $7,500.00 | $7,500.00 | $11,500.00 | $11,500.00 | $0.00 | |||||
| 4 | Furnish & Place Metal Roof On Oil Storage Building | 1 | L.S. | $2,200.00 | $2,200.00 | $1,600.00 | $1,600.00 | $0.00 | |||||
| 5 | Replace Gutter System On Hatchery Shop | 1 | L.S. | $500.00 | $500.00 | $1,400.00 | $1,400.00 | $0.00 | |||||
| $18,000.00 | $27,000.00 | $0.00 | |||||||||||
10/13/2026