IOWA DEPARTMENT OF NATURAL RESOURCES |
|
| Bids For: | Location: | Lost Island Lake | Date: 9/16/2010 | Project No. |
| Fish barriers / Water Control | County: | PALO ALTO | Time: 11:00 a.m. | 11-01-74-01 |
1 | 2 | 3 | |||||||||||
| Estimated Cost: | Contractor: | Landwehr Construction, Inc. | |||||||||||
| Funding Source: 100% Lake Restoration, | 846 S. 33rd St PO Box 1086 | ||||||||||||
| St. Cloud MN 56301 | |||||||||||||
| Plan Sets Requested: 7 | Quantities | 800-456-1284 | |||||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | BS-Mobilization | 1 | L.S. | $10,608.49 | $10,608.49 | $0.00 | $0.00 | ||||||
| 2 | BS-Site Preparation | 1 | L.S. | $953.00 | $953.00 | $0.00 | $0.00 | ||||||
| 3 | BS-Embankment Construction | 873 | C.Y. | $10.40 | $9,079.20 | $0.00 | $0.00 | ||||||
| 4 | BS-Excavation, Outlet Channel | 1720 | C.Y. | $8.20 | $14,104.00 | $0.00 | $0.00 | ||||||
| 5 | BS-Excavation, Inlet Channel | 3606 | C.Y. | $3.20 | $11,539.20 | $0.00 | $0.00 | ||||||
| 6 | BS-Excavation, Middle Barringer Slough | 2554 | C.Y. | $6.05 | $15,451.70 | $0.00 | $0.00 | ||||||
| 7 | BS-Revetment, Class II Riprap | 60 | C.Y. | $59.00 | $3,540.00 | $0.00 | $0.00 | ||||||
| 8 | BS-Revetment, Class III Riprap | 50 | C.Y. | $75.00 | $3,750.00 | $0.00 | $0.00 | ||||||
| 9 | BS-Bedding, 3/4" - 1 1/4" Cr. Stone | 100 | C.Y. | $28.40 | $2,840.00 | $0.00 | $0.00 | ||||||
| 10 | BS-RCB, Twin 9' X 5' | 24 | L.F. | $1,499.00 | $35,976.00 | $0.00 | $0.00 | ||||||
| 11 | BS-RCB Weir Section, Twin 9' X 5' | 12 | L.F. | $721.00 | $8,652.00 | $0.00 | $0.00 | ||||||
| 12 | BS-RCB Weir Section, Twin 9' X 5' w/Buttress Walls | 6 | L.F. | $856.00 | $5,136.00 | $0.00 | $0.00 | ||||||
| 13 | BS-RCB Sloped End Section, Twin 9' X 5' | 10 | L.F. | $700.00 | $7,000.00 | $0.00 | $0.00 | ||||||
| 14 | BS-3'-2" Precast Dropped End Walls | 1 | L.S. | $3,158.00 | $3,158.00 | $0.00 | $0.00 | ||||||
| 15 | BS-Curb, Precast, 12" X 18" | 1 | L.S. | $614.00 | $614.00 | $0.00 | $0.00 | ||||||
| 16 | BS-Curb, Precast, 12" X 12" | 1 | L.S. | $615.00 | $615.00 | $0.00 | $0.00 | ||||||
| 17 | BS-Concrete, Cast In Place | 5 | C.Y. | $1,348.00 | $6,740.00 | $0.00 | $0.00 | ||||||
| 18 | BS-Stoplog Guides, Galvanized System | 1 | L.S. | $5,123.00 | $5,123.00 | $0.00 | $0.00 | ||||||
| 19 | BS-Aluminum Stoplogs - Cleaning Rake | 1 | L.S. | $7,493.00 | $7,493.00 | $0.00 | $0.00 | ||||||
| 20 | BS-Horizontal Fish Fingers | 1 | L.S. | $12,656.00 | $12,656.00 | $0.00 | $0.00 | ||||||
| 21 | BS-Catwalk Components | 1 | L.S. | $22,500.00 | $22,500.00 | $0.00 | $0.00 | ||||||
| 22 | BS-Aluminum Fish Fingers/Winch | 1 | L.S. | $16,924.00 | $16,924.00 | $0.00 | $0.00 | ||||||
| 23 | BS-Removal of Existing Structures | 1 | L.S. | $2,710.00 | $2,710.00 | $0.00 | $0.00 | ||||||
| 24 | BS-Soil Erosion and Pollution Control | 1 | L.S. | $2,740.00 | $2,740.00 | $0.00 | $0.00 | ||||||
| 25 | BS-Seeding and Mulching | 3.5 | Acres | $1,144.00 | $4,004.00 | $0.00 | $0.00 | ||||||
| 26 | DU-Mobilization | 1 | L.S. | $9,080.00 | $9,080.00 | $0.00 | $0.00 | ||||||
| 27 | DU-Site Preparation | 1 | L.S. | $3,794.00 | $3,794.00 | $0.00 | $0.00 | ||||||
| 28 | DU-Excavation, Outlet Channel | 1900 | C.Y. | $4.34 | $8,246.00 | $0.00 | $0.00 | ||||||
| 29 | DU-Revetment, Class II Riprap | 85 | C.Y. | $59.50 | $5,057.50 | $0.00 | $0.00 | ||||||
| 30 | DU-Culvert, Metal CMP, 15" Dia. | 22 | L.F. | $23.00 | $506.00 | $0.00 | $0.00 | ||||||
| 31 | DU-Cast In Place Concrete | 32 | C.Y. | $1,027.00 | $32,864.00 | $0.00 | $0.00 | ||||||
| 32 | DU-Structural Steel | 1 | L.S. | $7,340.00 | $7,340.00 | $0.00 | $0.00 | ||||||
| 33 | DU-Soil Erosion & Pollution Control | 1 | L.S. | $1,750.00 | $1,750.00 | $0.00 | $0.00 | ||||||
| 34 | DU-Traffic Control | 1 | L.S. | $590.00 | $590.00 | $0.00 | $0.00 | ||||||
| 35 | DU-Seeding and Mulching | 2 | Acres | $1,144.00 | $2,288.00 | $0.00 | $0.00 | ||||||
| 36 | BM-Mobilization | 1 | L.S. | $2,220.00 | $2,220.00 | $0.00 | $0.00 | ||||||
| 37 | BM-Site Preparation | 1 | L.S. | $2,410.00 | $2,410.00 | $0.00 | $0.00 | ||||||
| 38 | BM-Excavation | 110 | C.Y. | $9.72 | $1,069.20 | $0.00 | $0.00 | ||||||
| 39 | BM-Embankment Construction | 181 | C.Y. | $15.00 | $2,715.00 | $0.00 | $0.00 | ||||||
| 40 | BM-Revetment, Class II Riprap | 72 | C.Y. | $59.40 | $4,276.80 | $0.00 | $0.00 | ||||||
| 41 | BM-IA Class III Aggregate | 36 | C.Y. | $23.90 | $860.40 | $0.00 | $0.00 | ||||||
| 42 | BM-Bedding, 3/4" - 1 1/4" Cr. Stone | 60 | C.Y. | $33.00 | $1,980.00 | $0.00 | $0.00 | ||||||
| 43 | BM-RCB, 12' X 4' Single (Furnish & Install) | 18 | L.F. | $824.00 | $14,832.00 | $0.00 | $0.00 | ||||||
| 44 | BM-RCB, 12' X 4' (Install Only) | 12 | L.F. | $1,329.00 | $15,948.00 | $0.00 | $0.00 | ||||||
| 45 | BM-End Section, Single BCB Sloped | 8 | L.F. | $790.00 | $6,320.00 | $0.00 | $0.00 | ||||||
| 46 | BM-3'-2" Precast Dropped End Wall | 1 | L.S. | $1,162.00 | $1,162.00 | $0.00 | $0.00 | ||||||
| 47 | BM-Cast In Place Concrete | 12 | C.Y. | $819.00 | $9,828.00 | $0.00 | $0.00 | ||||||
| 48 | BM-Stoplog Guides, Galvanized System | 1 | L.S. | $2,916.00 | $2,916.00 | $0.00 | $0.00 | ||||||
| 49 | BM-Aluminum Stoplogs - Catwalk Components | 1 | L.S. | $9,874.00 | $9,874.00 | $0.00 | $0.00 | ||||||
| 50 | BM-Removal of Existing Structures | 1 | L.S. | $1,064.00 | $1,064.00 | $0.00 | $0.00 | ||||||
| 51 | BM-Floating Silt Fence | 1 | L.S. | $4,290.00 | $4,290.00 | $0.00 | $0.00 | ||||||
| 52 | BM-Cofferdam/Dewatering | 1 | L.S. | $12,500.00 | $12,500.00 | $0.00 | $0.00 | ||||||
| 53 | BM-Seeding and Mulching | 0.5 | Acres | $1,144.00 | $572.00 | $0.00 | $0.00 | ||||||
| 54 | BW-Mobilization | 1 | L.S. | $8,823.00 | $8,823.00 | $0.00 | $0.00 | ||||||
| 55 | BW-Site Preparation | 1 | L.S. | $944.00 | $944.00 | $0.00 | $0.00 | ||||||
| 56 | BW-Excavation | 1189 | C.Y. | $10.95 | $13,019.55 | $0.00 | $0.00 | ||||||
| 57 | BW-Revetment, Class II Riprap | 30 | C.Y. | $59.00 | $1,770.00 | $0.00 | $0.00 | ||||||
| 58 | BW-Revetment, Class III Riprap | 36 | C.Y. | $74.00 | $2,664.00 | $0.00 | $0.00 | ||||||
| 59 | BW-IA Class III Aggregate | 84 | C.Y. | $22.50 | $1,890.00 | $0.00 | $0.00 | ||||||
| 60 | BW-Bedding, 3/4" - 1 1/4" Cr. Stone | 84 | C.Y. | $28.40 | $2,385.60 | $0.00 | $0.00 | ||||||
| 61 | BW-Surfacing, Class "A" Roadstone | 72 | C.Y. | $59.00 | $4,248.00 | $0.00 | $0.00 | ||||||
| 62 | BW-RCB, 6' X 4' Twin | 90 | L.F. | $949.00 | $85,410.00 | $0.00 | $0.00 | ||||||
| 63 | BW-RCB Weir Section, Twin 6' X 4' | 6 | L.F. | $930.00 | $5,580.00 | $0.00 | $0.00 | ||||||
| 64 | BW-RCB Sloped End Section, Twin 6' X 4' | 6 | L.F. | $937.00 | $5,622.00 | $0.00 | $0.00 | ||||||
| 65 | BW-3'-2" Precast Dropped End Wall | 1 | L.S. | $2,440.00 | $2,440.00 | $0.00 | $0.00 | ||||||
| 66 | BW-Curb, Precast, 12" X 12" | 1 | L.S. | $614.00 | $614.00 | $0.00 | $0.00 | ||||||
| 67 | BW-Cast In Place Concrete | 0.5 | C.Y. | $1,842.00 | $921.00 | $0.00 | $0.00 | ||||||
| 68 | BW-Stoplog Guides, Galvanized System | 1 | L.S. | $2,500.00 | $2,500.00 | $0.00 | $0.00 | ||||||
| 69 | BW-Aluminum Stoplogs - Cleaning Rake | 1 | L.S. | $1,493.00 | $1,493.00 | $0.00 | $0.00 | ||||||
| 70 | BW-Horizontal Fish Fingers | 1 | L.S. | $3,325.00 | $3,325.00 | $0.00 | $0.00 | ||||||
| 71 | BW-Catwalk Components | 1 | L.S. | $7,318.00 | $7,318.00 | $0.00 | $0.00 | ||||||
| 72 | BW-Aluminum Fish Fingers/Winch | 1 | L.S. | $5,659.00 | $5,659.00 | $0.00 | $0.00 | ||||||
| 73 | BW-Removal of Existing Structures | 1 | L.S. | $1,982.00 | $1,982.00 | $0.00 | $0.00 | ||||||
| 74 | BW-Soil Erosion & Pollution Control | 1 | L.S. | $2,924.00 | $2,924.00 | $0.00 | $0.00 | ||||||
| 75 | BW-Traffic Control | 1 | L.S. | $2,860.00 | $2,860.00 | $0.00 | $0.00 | ||||||
| 76 | BW-Seeding & Mulching | 0.5 | Acres | $1,144.00 | $572.00 | $0.00 | $0.00 | ||||||
| 77 | LI-Mobilization | 1 | L.S. | $11,420.00 | $11,420.00 | $0.00 | $0.00 | ||||||
| 78 | LI-Site Preparation | 1 | L.S. | $1,820.00 | $1,820.00 | $0.00 | $0.00 | ||||||
| 79 | LI-Embankment Construction | 367 | C.Y. | $12.68 | $4,653.56 | $0.00 | $0.00 | ||||||
| 80 | LI-Revetment, Class II Riprap | 96 | C.Y. | $50.00 | $4,800.00 | $0.00 | $0.00 | ||||||
| 81 | LI-Revetment, Class III Riprap | 154 | C.Y. | $65.00 | $10,010.00 | $0.00 | $0.00 | ||||||
| 82 | LI-IA Class III Aggregate | 30 | C.Y. | $23.00 | $690.00 | $0.00 | $0.00 | ||||||
| 83 | LI-Bedding, 3/4" - 1 1/4" Cr. Stone | 30 | C.Y. | $38.00 | $1,140.00 | $0.00 | $0.00 | ||||||
| 84 | LI-RCB, Single 9' X 5' | 18 | L.F. | $894.00 | $16,092.00 | $0.00 | $0.00 | ||||||
| 85 | LI-RCB, Single 9' X 5' (Modified) | 6 | L.F. | $699.00 | $4,194.00 | $0.00 | $0.00 | ||||||
| 86 | LI-RCB Sloped End Section, Single 9' X 5' | 10 | L.F. | $485.00 | $4,850.00 | $0.00 | $0.00 | ||||||
| 87 | LI-3'-2" Precast Dropped End Wall | 1 | L.S. | $984.00 | $984.00 | $0.00 | $0.00 | ||||||
| 88 | LI-Curb, Precast, 12" X 12" | 1 | L.S. | $1,230.00 | $1,230.00 | $0.00 | $0.00 | ||||||
| 89 | LI-Cast In Place Concrete | 17 | C.Y. | $595.00 | $10,115.00 | $0.00 | $0.00 | ||||||
| 90 | LI-Sheet Pile - Materials | 1921 | S.F. | $15.70 | $30,159.70 | $0.00 | $0.00 | ||||||
| 91 | LI-Sheet Pile - Installation | 1921 | S.F. | $6.80 | $13,062.80 | $0.00 | $0.00 | ||||||
| 92 | LI-Pile Cap, Guides, Channels, Angles, etc. | 1 | L.S. | $32,853.00 | $32,853.00 | $0.00 | $0.00 | ||||||
| 93 | LI-Aluminum Fish Screens & Rake | 1 | L.S. | $23,300.00 | $23,300.00 | $0.00 | $0.00 | ||||||
| 94 | LI- Stoplog & Catwalk Components | 1 | L.S. | $21,505.00 | $21,505.00 | $0.00 | $0.00 | ||||||
| 95 | LI-Aluminum Stoplogs | 1 | L.S. | $3,409.00 | $3,409.00 | $0.00 | $0.00 | ||||||
| 96 | LI-Floating Silt Fence | 1 | L.S. | $4,255.00 | $4,255.00 | $0.00 | $0.00 | ||||||
| 97 | LI-Cofferdam/Dewatering | 1 | L.S. | $33,800.00 | $33,800.00 | $0.00 | $0.00 | ||||||
| 98 | LI-Access Road Resurfacing | 260 | C.Y. | $24.33 | $6,325.80 | $0.00 | $0.00 | ||||||
| 99 | LI-Removal of Existing Structures | 1 | L.S. | $535.00 | $535.00 | $0.00 | $0.00 | ||||||
| 100 | LI-Seeding & Mulching | 0.5 | Acres | $1,145.00 | $572.50 | $0.00 | $0.00 | ||||||
| $787,000.00 | $0.00 | $0.00 | |||||||||||
10/13/2026