| Bids For: | Location: | Storm Lake State Marina | Date: 9/8/2011 | Project No. |
| Boat Ramp Maneuvering Area Paving Extension | County: | BUENA VISTA | Time: 3:00 p.m. | 11-01-11-01 |
1 | 2 | 3 | |||||||||||
| Estimated Cost: $25,500.00 | Contractor: | K P Construction | |||||||||||
| Funding Source: 100% Marine Fuel Tax, | 1624 210th st PO Box 397 | ||||||||||||
| Sergeant Bluff IA 51054 | |||||||||||||
| Plan Sets Requested: 0 | Quantities | 712-943-4355 | |||||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Pavement Removal | 125 | S.Y. | $12.00 | $1,500.00 | $0.00 | $0.00 | ||||||
| 2 | Full Depth Saw Cut | 56 | L.F. | $10.00 | $560.00 | $0.00 | $0.00 | ||||||
| 3 | Granular Sub-base | 38 | Tons | $35.00 | $1,330.00 | $0.00 | $0.00 | ||||||
| 4 | 6" PCC Pavement (Class C) | 187 | S.Y. | $46.00 | $8,602.00 | $0.00 | $0.00 | ||||||
| 5 | 6" PCC Curb | 154 | L.F. | $8.00 | $1,232.00 | $0.00 | $0.00 | ||||||
| 6 | 18" Long #5 Dowel Bars | 56 | Each | $9.00 | $504.00 | $0.00 | $0.00 | ||||||
| 7 | Grading & Site Restoration | 1 | L.S. | $1,000.00 | $1,000.00 | $0.00 | $0.00 | ||||||
| 8 | Erosion Control (Straw Mat) | 100 | S.F. | $3.00 | $300.00 | $0.00 | $0.00 | ||||||
| 9 | Seeding | 1 | L.S. | $1,000.00 | $1,000.00 | $0.00 | $0.00 | ||||||
| $16,028.00 | $0.00 | $0.00 | |||||||||||