IOWA DEPARTMENT OF NATURAL RESOURCES |
|
| Bids For: | Location: | Brushy Creek State Park | Date: 11/18/2010 | Project No. |
| Sediment Control Structures | County: | WEBSTER | Time: 3:00 p.m. | 11-02-94-06 |
1 | 2 | 3 | |||||||||||
| Estimated Cost: $64,920.00 | Contractor: | Carnarvon Sand & Gravel | Richards Construction Co Inc | Ingraham Construction | |||||||||
| Funding Source: 75% Federal-EPA, 25% Lake Restoration, | 205 E 1st St PO Box 66 | 2721 Sierra Ave | 131 - 2nd Street PO Box 515 | ||||||||||
| Wall Lake IA 51466 | Sac City IA 50583 | Webster City IA 50595 | |||||||||||
| Plan Sets Requested: 0 | Quantities | 712-664-2511 | 712-662-4421 | 515-832-9958 | |||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Sediment Control Structure 1 | 1 | L.S. | $3,844.00 | $3,844.00 | $5,500.00 | $5,500.00 | $6,244.60 | $6,244.60 | ||||
| 2 | Sediment Control Structure 2 | 1 | L.S. | $4,644.00 | $4,644.00 | $6,200.00 | $6,200.00 | $7,258.10 | $7,258.10 | ||||
| 3 | Sediment Control Structure 3 | 1 | L.S. | $3,257.00 | $3,257.00 | $5,700.00 | $5,700.00 | $5,676.60 | $5,676.60 | ||||
| 4 | Sediment Control Structure 4 | 1 | L.S. | $4,360.00 | $4,360.00 | $5,500.00 | $5,500.00 | $6,969.10 | $6,969.10 | ||||
| 5 | Sediment Control Structure 5 | 1 | L.S. | $3,139.00 | $3,139.00 | $6,000.00 | $6,000.00 | $5,789.60 | $5,789.60 | ||||
| 6 | Sediment Control Structure 6 | 1 | L.S. | $5,941.00 | $5,941.00 | $7,500.00 | $7,500.00 | $8,086.60 | $8,086.60 | ||||
| 7 | Sediment Control Structure 8 | 1 | L.S. | $8,192.00 | $8,192.00 | $8,700.00 | $8,700.00 | $9,976.60 | $9,976.60 | ||||
| 8 | Sediment Control Structure 9 | 1 | L.S. | $2,831.00 | $2,831.00 | $4,500.00 | $4,500.00 | $5,497.60 | $5,497.60 | ||||
| 9 | Sediment Control Structure 11 N | 1 | L.S. | $7,410.00 | $7,410.00 | $8,200.00 | $8,200.00 | $9,399.70 | $9,399.70 | ||||
| 10 | Sediment Control Structure 11 S | 1 | L.S. | $5,739.00 | $5,739.00 | $8,200.00 | $8,200.00 | $7,809.10 | $7,809.10 | ||||
| 11 | Sediment Control Structure 12 | 1 | L.S. | $2,782.00 | $2,782.00 | $5,000.00 | $5,000.00 | $5,397.10 | $5,397.10 | ||||
| 12 | Sediment Control Structure 13 W | 1 | L.S. | $2,369.00 | $2,369.00 | $4,800.00 | $4,800.00 | $4,769.60 | $4,769.60 | ||||
| 13 | Sediment Control Structure 14 | 1 | L.S. | $10,110.00 | $10,110.00 | $11,500.00 | $11,500.00 | $15,500.00 | $15,500.00 | ||||
| $64,618.00 | $87,300.00 | $98,374.30 | |||||||||||
4 | 5 | 6 | |||||||||||
| Estimated Cost: $64,920.00 | Contractor: | Steger Construction Inc | |||||||||||
| Funding Source: 75% Federal-EPA, 25% Lake Restoration, | 3297 Vine Rd | ||||||||||||
| Dyersville IA 52040 | |||||||||||||
| Plan Sets Requested: 0 | Quantities | 563-875-7876 | |||||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Sediment Control Structure 1 | 1 | L.S. | $9,025.00 | $9,025.00 | $0.00 | $0.00 | ||||||
| 2 | Sediment Control Structure 2 | 1 | L.S. | $16,523.50 | $16,523.50 | $0.00 | $0.00 | ||||||
| 3 | Sediment Control Structure 3 | 1 | L.S. | $8,262.50 | $8,262.50 | $0.00 | $0.00 | ||||||
| 4 | Sediment Control Structure 4 | 1 | L.S. | $11,372.50 | $11,372.50 | $0.00 | $0.00 | ||||||
| 5 | Sediment Control Structure 5 | 1 | L.S. | $8,147.00 | $8,147.00 | $0.00 | $0.00 | ||||||
| 6 | Sediment Control Structure 6 | 1 | L.S. | $14,810.00 | $14,810.00 | $0.00 | $0.00 | ||||||
| 7 | Sediment Control Structure 8 | 1 | L.S. | $25,200.00 | $25,200.00 | $0.00 | $0.00 | ||||||
| 8 | Sediment Control Structure 9 | 1 | L.S. | $9,151.00 | $9,151.00 | $0.00 | $0.00 | ||||||
| 9 | Sediment Control Structure 11 N | 1 | L.S. | $22,800.00 | $22,800.00 | $0.00 | $0.00 | ||||||
| 10 | Sediment Control Structure 11 S | 1 | L.S. | $19,477.50 | $19,477.50 | $0.00 | $0.00 | ||||||
| 11 | Sediment Control Structure 12 | 1 | L.S. | $8,717.50 | $8,717.50 | $0.00 | $0.00 | ||||||
| 12 | Sediment Control Structure 13 W | 1 | L.S. | $7,490.00 | $7,490.00 | $0.00 | $0.00 | ||||||
| 13 | Sediment Control Structure 14 | 1 | L.S. | $15,000.00 | $15,000.00 | $0.00 | $0.00 | ||||||
| $175,976.50 | $0.00 | $0.00 | |||||||||||