IOWA DEPARTMENT OF NATURAL RESOURCES |
|
| Bids For: | Location: | Yellow River State Forest | Date: 3/22/2012 | Project No. |
| Repair pond spillway/dike | County: | ALLAMAKEE | Time: 3:00 p.m. | 11-03-03-01 |
1 | 2 | 3 | |||||||||||
| Estimated Cost: $5,000.00 | Contractor: | Skyline Construction Inc | Riehm Construction Company | Lansing Brothers Construction Co. Inc. | |||||||||
| Funding Source: 100% REAP OS Acquisition & Development, | PO Box 127 | 2340 - 9th St SW | 101 E 1st ST PO Box 36 | ||||||||||
| Decorah IA 52101 | Waukon IA 52172 | Luxemburg IA 52056 | |||||||||||
| Plan Sets Requested: 0 | Quantities | 563-382-2933 | 563-568-3314 | 563-543-7360 | |||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Mobilization | 1 | L.S. | $1,061.93 | $1,061.93 | $1,000.00 | $1,000.00 | $2,000.00 | $2,000.00 | ||||
| 2 | Repair Outlet Spillway | 50 | C.Y. | $5.00 | $250.00 | $18.00 | $900.00 | $15.00 | $750.00 | ||||
| 3 | Erosion Fabric Under Revetment | 30 | S.Y. | $2.00 | $60.00 | $13.00 | $390.00 | $6.00 | $180.00 | ||||
| 4 | Revetment, Class 'D' | 54 | Tons | $20.00 | $1,080.00 | $20.00 | $1,080.00 | $30.00 | $1,620.00 | ||||
| 5 | Stabilizing Crop Seeding | 0.25 | Acres | $2,500.00 | $625.00 | $1,500.00 | $375.00 | $1,200.00 | $300.00 | ||||
| $3,076.93 | $3,745.00 | $4,850.00 | |||||||||||
4 | 5 | 6 | |||||||||||
| Estimated Cost: $5,000.00 | Contractor: | Matt Construction Inc | Connolly Construction Inc | Eastern Iowa Excavating & Concrete LLC | |||||||||
| Funding Source: 100% REAP OS Acquisition & Development, | 203 Y Ave | 18409 N Cascade Rd PO Box 68 | 121 Nixon St SE PO Box 189 | ||||||||||
| Sumner IA 50674 | Peosta IA 52068 | Cascade IA 52033 | |||||||||||
| Plan Sets Requested: 0 | Quantities | 563-578-8418 | 563-876-3225 | 563-852-5120 | |||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Mobilization | 1 | L.S. | $2,000.00 | $2,000.00 | $4,000.00 | $4,000.00 | $5,500.00 | $5,500.00 | ||||
| 2 | Repair Outlet Spillway | 50 | C.Y. | $20.00 | $1,000.00 | $20.00 | $1,000.00 | $15.00 | $750.00 | ||||
| 3 | Erosion Fabric Under Revetment | 30 | S.Y. | $5.00 | $150.00 | $5.75 | $172.50 | $5.50 | $165.00 | ||||
| 4 | Revetment, Class 'D' | 54 | Tons | $35.00 | $1,890.00 | $50.00 | $2,700.00 | $25.50 | $1,377.00 | ||||
| 5 | Stabilizing Crop Seeding | 0.25 | Acres | $5,000.00 | $1,250.00 | $3,250.00 | $812.50 | $4,300.00 | $1,075.00 | ||||
| $6,290.00 | $8,685.00 | $8,867.00 | |||||||||||