IOWA DEPARTMENT OF NATURAL RESOURCES |
|
| Bids For: | Location: | Dolliver State Park | Date: 7/1/2010 | Project No. |
| Repair Flood Damages | County: | WEBSTER | Time: 3:00 p.m. | 10-02-94-05 |
1 | 2 | 3 | |||||||||||
| Estimated Cost: $16,280.00 | Contractor: | Ingraham Construction | Richards Construction Co Inc | Fort Dodge Asphalt Co | |||||||||
| Funding Source: 100% Executive Council, | 131 - 2nd Street PO Box 515 | 2721 Sierra Ave | 2516 7th Ave S | ||||||||||
| Webster City IA 50595 | Sac City IA 50583 | Fort Dodge IA 50501 | |||||||||||
| Plan Sets Requested: 0 | Quantities | 515-832-9958 | 712-662-4421 | 515-573-3124 | |||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Class “D” Riprap/w fabric -Boat Ramp parking scoured area | 120 | Tons | $34.00 | $4,080.00 | $47.80 | $5,736.00 | $48.20 | $5,784.00 | ||||
| 2 | Class “A” Limestone -Boat Ramp parking scoured area | 65 | Tons | $15.00 | $975.00 | $17.22 | $1,119.30 | $46.00 | $2,990.00 | ||||
| 3 | Class “A” Limestone – Parking lot at campground | 36 | Tons | $15.00 | $540.00 | $17.22 | $619.92 | $46.00 | $1,656.00 | ||||
| 4 | Class “A” Limestone – Parking lot at playground | 215 | Tons | $15.00 | $3,225.00 | $17.22 | $3,702.30 | $44.50 | $9,567.50 | ||||
| 5 | Class “D” Riprap - Creek | 50 | Tons | $34.00 | $1,700.00 | $47.80 | $2,390.00 | $46.00 | $2,300.00 | ||||
| $10,520.00 | $13,567.52 | $22,297.50 | |||||||||||
10/12/2026