IOWA DEPARTMENT OF NATURAL RESOURCES
ENGINEERING BUREAU

INFORMAL BID TAB
NOTICE: This document represents bids that were opened on the letting date and may be subject to further review. This is not the official bid tab.

 Bids For:  Location:   Lake Sugema  Date: 10/7/2010  Project No.  
  Lake Sugema FEMA shoreline work  County:   VAN BUREN  Time: 3:00 p.m.  10-06-89-04

 

 
1
2
3
Estimated Cost: $37,800.00
Contractor: 
Buford Dozing & ExcavatingCole Construction Company IncDeLong Construction Inc
Funding Source: 90% Federal-FEMA 1, 10% FY09 Supplemental Appropriation, 29623 260th St
24100 Queen Ave
1320 N 8th Ave
PO Box 488
Bonaparte IA  52620Keosauqua IA  525658329Washington IA  52353
Plan Sets Requested: 0
Quantities
319-470-1492319-592-3103319-653-3334
No.Description:No.UnitUnit Price AmountUnit Price AmountUnit Price Amount
1Class 10 Excavation94C.Y.$1.00$94.00 $10.00$940.00 $25.00$2,350.00 
2Engineering Fabric804S.Y.$1.25$1,005.00 $3.00$2,412.00 $3.00$2,412.00 
3Class E Revetment554Tons$44.17$24,470.18 $47.00$26,038.00 $52.00$28,808.00 
4Granular Surfacing, Class A Crushed Stone167Tons$21.02$3,510.34 $17.50$2,922.50 $31.50$5,260.50 
      $29,079.52  $32,312.50  $38,830.50 
 



 

10/13/2026