 Bids For:  Location:   Seneca WMA-Struecker Tract  Date: 7/1/2010  Project No.  
  install water control structure  County:   KOSSUTH  Time: 3:00 p.m.  10-01-55-02

 

 
1
2
3
Estimated Cost:
Contractor: 
Richards Construction Co IncRedings Gravel & Excavating
Funding Source: 100% Federal-EPA, 2721 Sierra Ave
2001 East Oak St
PO Box 158

Sac City IA  50583Algona IA  50511  
Plan Sets Requested: 0
Quantities
712-662-4421515-295-3661
No.Description:No.UnitUnit Price AmountUnit Price AmountUnit Price Amount
18" CMP20L.F.$21.00$420.00 $88.80$1,776.00 $0.00 
215" CMP Tee w/ Riser Pipe1L.S.$1,500.00$1,500.00 $2,900.00$2,900.00 $0.00 
3Water Control Structure1L.S.$3,400.00$3,400.00 $3,475.00$3,475.00 $0.00 
410" PE Tubing (Non-Perf)140L.F.$28.00$3,920.00 $31.21$4,369.40 $0.00 
510" Inlet1L.S.$700.00$700.00 $892.60$892.60 $0.00 
6Dewatering1L.S.$4,000.00$4,000.00 $4,900.00$4,900.00 $0.00 
      $13,940.00  $18,313.00  $0.00 
 



 