IOWA DEPARTMENT OF NATURAL RESOURCES |
|
| Bids For: | Location: | Springbrook State Park | Date: 9/15/2011 | Project No. |
| Sherburne cabin road | County: | GUTHRIE | Time: 11:00 a.m. | 10-04-39-04 |
1 | 2 | 3 | |||||||||||
| Estimated Cost: $190,000.00 | Contractor: | Concrete Technologies Inc | Precision Concrete Services Inc | TK Concrete Inc | |||||||||
| Funding Source: 100% Park & Institutional Road Fund, | 3809 NW 109th St Suite D | 1207 Sunnyside Lane, Ste A | 1608 Fifield Rd PO Box 111 | ||||||||||
| Urbandale IA 50322 | Atlantic IA 50022 | Pella IA 50219 | |||||||||||
| Plan Sets Requested: 4 | Quantities | 515-252-1650 | 712-243-2419 | 641-628-4590 | |||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Clearing and Grubbing | 1.48 | Acres | $5,250.00 | $7,770.00 | $5,640.20 | $8,347.496 | $7,000.00 | $10,360.00 | ||||
| 2 | Excavation, Class 10, Roadway and Borrow | 2616 | C.Y. | $7.35 | $19,227.60 | $13.00 | $34,008.00 | $8.00 | $20,928.00 | ||||
| 3 | Special Backfill | 917 | Tons | $31.50 | $28,885.50 | $21.25 | $19,486.25 | $22.00 | $20,174.00 | ||||
| 4 | Subgrade Stabilization Material, Polymer Grid | 3170 | S.Y. | $4.25 | $13,472.50 | $3.25 | $10,302.50 | $2.50 | $7,925.00 | ||||
| 5 | Granular Shoulder, Type A | 196 | Tons | $36.75 | $7,203.00 | $20.90 | $4,096.40 | $25.00 | $4,900.00 | ||||
| 6 | Standard or Slip Form PCC Pavement, Class C, Class 2 Durability, 6" | 2332 | S.Y. | $32.00 | $74,624.00 | $42.75 | $99,693.00 | $42.75 | $99,693.00 | ||||
| 7 | Culvert, RCP, 18" Dia. | 138 | L.F. | $46.25 | $6,382.50 | $57.75 | $7,969.50 | $50.00 | $6,900.00 | ||||
| 8 | Aprons, Concrete, 18" Dia. | 5 | Each | $1,470.00 | $7,350.00 | $1,290.00 | $6,450.00 | $1,500.00 | $7,500.00 | ||||
| 9 | Intake, SW-507 Modified | 3 | Each | $3,990.00 | $11,970.00 | $4,200.00 | $12,600.00 | $5,000.00 | $15,000.00 | ||||
| 10 | Revetment, Class "E" Riprap | 425 | Tons | $42.00 | $17,850.00 | $41.25 | $17,531.25 | $50.00 | $21,250.00 | ||||
| 11 | HMA Removal | 334 | S.Y. | $3.15 | $1,052.10 | $11.68 | $3,901.12 | $12.00 | $4,008.00 | ||||
| 12 | Curb Stop, Precast, 7' | 6 | Each | $126.00 | $756.00 | $150.00 | $900.00 | $200.00 | $1,200.00 | ||||
| 13 | Construction Survey | 1 | L.S. | $3,675.00 | $3,675.00 | $7,500.00 | $7,500.00 | $4,250.00 | $4,250.00 | ||||
| 14 | Traffic Control | 1 | L.S. | $2,100.00 | $2,100.00 | $3,500.00 | $3,500.00 | $2,500.00 | $2,500.00 | ||||
| 15 | Mobilization | 1 | L.S. | $40,000.00 | $40,000.00 | $12,500.00 | $12,500.00 | $35,800.00 | $35,800.00 | ||||
| 16 | Site Restoration | 1 | L.S. | $10,500.00 | $10,500.00 | $6,000.00 | $6,000.00 | $7,500.00 | $7,500.00 | ||||
| $252,818.20 | $254,785.516 | $269,888.00 | |||||||||||