IOWA DEPARTMENT OF NATURAL RESOURCES
ENGINEERING BUREAU

INFORMAL BID TAB
NOTICE: This document represents bids that were opened on the letting date and may be subject to further review. This is not the official bid tab.

 Bids For:  Location:   Littleton Iowa  Date: 11/15/2018  Project No.  
  Dam Mitigation  County:   BUCHANAN  Time: 11:00 a.m.  10-03-10-01

 

 
1
2
3
Estimated Cost: $470,000.00
Contractor: 
Veit & Company, Inc.Dave Schmitt Construction Company Inc.Skyline Construction Inc.
Funding Source: 79% Marine Fuel Tax, 21% Federal-Other, 14000 Veit Place
250 50th Ave SW
900 Montgomery St
Rogers MN  55374Cedar Rapids IA  52404Decorah IA  52101
Plan Sets Requested: 7
Quantities
7634282242(319) 365-86695633822933
No.Description:No.UnitUnit Price AmountUnit Price AmountUnit Price Amount
1Mobilization1L.S.$54,000.00$54,000.00 $36,000.00$36,000.00 $189,200.00$189,200.00 
2Clearing and Grubbing1L.S.$4,200.00$4,200.00 $9,765.00$9,765.00 $1,950.00$1,950.00 
3Dam Removal1L.S.$75,500.00$75,500.00 $86,300.00$86,300.00 $27,500.00$27,500.00 
4Excavation, Export1550C.Y.$17.05$26,427.50 $34.50$53,475.00 $15.99$24,784.50 
5Base Stone, Class "E" Revetment4500Tons$37.35$168,075.00 $34.50$155,250.00 $45.00$202,500.00 
66" Minus Choke Stone1160Tons$33.65$39,034.00 $35.50$41,180.00 $26.00$30,160.00 
7Weir Stone (3.5'x3.0'x1.5' Min.)290Tons$160.25$46,472.50 $280.50$81,345.00 $175.50$50,895.00 
8Large Weir Stone (4.0'x5.0'x1.2' Min.)60Tons$277.00$16,620.00 $360.50$21,630.00 $250.50$15,030.00 
9Stabilized Construction Entrance30Tons$39.30$1,179.00 $57.25$1,717.50 $30.00$900.00 
10Erosion Control1L.S.$5,000.00$5,000.00 $1,750.00$1,750.00 $5,500.00$5,500.00 
11Seeding/Fertilizing/Mulching1L.S.$3,200.00$3,200.00 $2,750.00$2,750.00 $3,500.00$3,500.00 
      $439,708.00  $491,162.50  $551,919.50 
 
 
4
5
6
Estimated Cost: $470,000.00
Contractor: 
Tschiggfrie ExcavatingRay's Excavating, LLCCJ Moyna and Sons, Inc.
Funding Source: 79% Marine Fuel Tax, 21% Federal-Other, 425 Julien Dubuque Dr
PO Box 3280
404 E Union St
24412 Hwy 13
Dubuque IA  52003Edgewood IA  52042Elkader IA  52043
Plan Sets Requested: 7
Quantities
(563) 557-7450(563) 928-72905632451442
No.Description:No.UnitUnit Price AmountUnit Price AmountUnit Price Amount
1Mobilization1L.S.$150,000.00$150,000.00 $20,000.00$20,000.00 $370,000.00$370,000.00 
2Clearing and Grubbing1L.S.$4,900.00$4,900.00 $7,500.00$7,500.00 $8,500.00$8,500.00 
3Dam Removal1L.S.$182,500.00$182,500.00 $180,000.00$180,000.00 $235,000.00$235,000.00 
4Excavation, Export1550C.Y.$16.00$24,800.00 $12.00$18,600.00 $22.80$35,340.00 
5Base Stone, Class "E" Revetment4500Tons$54.10$243,450.00 $24.00$108,000.00 $46.50$209,250.00 
66" Minus Choke Stone1160Tons$72.00$83,520.00 $22.00$25,520.00 $38.50$44,660.00 
7Weir Stone (3.5'x3.0'x1.5' Min.)290Tons$301.00$87,290.00 $40.00$11,600.00 $95.80$27,782.00 
8Large Weir Stone (4.0'x5.0'x1.2' Min.)60Tons$251.00$15,060.00 $35.00$2,100.00 $186.50$11,190.00 
9Stabilized Construction Entrance30Tons$57.30$1,719.00 $15,000.00$450,000.00 $31.50$945.00 
10Erosion Control1L.S.$6,300.00$6,300.00 $10,000.00$10,000.00 $6,500.00$6,500.00 
11Seeding/Fertilizing/Mulching1L.S.$3,500.00$3,500.00 $0.00$0.00 $8,500.00$8,500.00 
      $803,039.00  $833,320.00  $957,667.00 
 


The following apparent low bidders were found to be Non-Responsive and/or Not Responsible. No determinations have been made regarding the Responsiveness and Responsibility of the bidders that are not the apparent low.


Ray's Excavating, LLC, Edgewood, IA
 

DNR reserves the right to modify this list as it reviews and inspects the bids received. DNR will update the bid tab accordingly.

7/18/2019