IOWA DEPARTMENT OF NATURAL RESOURCES |
|
| Bids For: | Location: | Sedan Bottoms WMA - Brown | Date: 6/17/2010 | Project No. |
| Wetland Restoration | County: | APPANOOSE | Time: 11:00 AM | 11-05-04-01 |
1 | 2 | 3 | |||||||||||
| Estimated Cost: $149,122.00 | Contractor: | Spring Lake Construction | Kevin Kent Construction | ||||||||||
| Funding Source: 100% Federal-NRCS, | 4123 SW 95th Place | 15157 US Hwy 34 | |||||||||||
| Polk City IA 50226 | Lucas IA 50151 | ||||||||||||
| Plan Sets Requested: 5 | Quantities | 515-965-6093 | 641-766-6126 | ||||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Mobilization | 1 | L.S. | $5,000.00 | $5,000.00 | $4,500.00 | $4,500.00 | $0.00 | |||||
| 2 | Site Preparation | 1 | L.S. | $1,000.00 | $1,000.00 | $5,000.00 | $5,000.00 | $0.00 | |||||
| 3 | Removal of Culvert | 1 | Each | $1,000.00 | $1,000.00 | $750.00 | $750.00 | $0.00 | |||||
| 4 | Removal of Tile | 570 | L.F. | $3.00 | $1,710.00 | $2.00 | $1,140.00 | $0.00 | |||||
| 5 | Excavation | 5050 | C.Y. | $1.25 | $6,312.50 | $1.85 | $9,342.50 | $0.00 | |||||
| 6 | Shallow Water Excavation | 41818 | C.Y. | $1.20 | $50,181.60 | $1.65 | $68,999.70 | $0.00 | |||||
| 7 | Earthfill | 20667 | C.Y. | $1.35 | $27,900.45 | $2.06 | $42,574.02 | $0.00 | |||||
| 8 | Principal Spillway, 84-in. SMP Riser, 48-in. SMP Conduit, Trash Rack, Anti-Seep | 1 | L.S. | $31,000.00 | $31,000.00 | $20,500.00 | $20,500.00 | $0.00 | |||||
| 9 | Macadam Stone Base | 30 | Tons | $50.00 | $1,500.00 | $40.00 | $1,200.00 | $0.00 | |||||
| 10 | Seeding, Islands | 5 | Acres | $350.00 | $1,750.00 | $1,200.00 | $6,000.00 | $0.00 | |||||
| 11 | Seeding & Mulch - Levee, Outlet Chute, Aux Spillway | 10 | Acres | $700.00 | $7,000.00 | $1,750.00 | $17,500.00 | $0.00 | |||||
| $134,354.55 | $177,506.22 | $0.00 | |||||||||||
10/12/2026