IOWA DEPARTMENT OF NATURAL RESOURCES |
|
| Bids For: | Location: | Guttenberg Hatchery fishing walkway | Date: 9/23/2010 | Project No. |
| walkway repair | County: | CLAYTON | Time: 3:00 p.m. | 10-03-22-01 |
1 | 2 | 3 | |||||||||||
| Estimated Cost: $5,000.00 | Contractor: | Burr Oak Springs Limited | Matt Construction Inc | Lansing Brothers Construction | |||||||||
| Funding Source: 100% REAP Land Management, | 2113 County Rd W-14 | 203 Y Ave | 101 E 1st St PO Box 36 | ||||||||||
| Ridgeway IA 52165 | Sumner IA 50674 | Luxemburg IA 52056 | |||||||||||
| Plan Sets Requested: 0 | Quantities | 563-737-3510 | 563-578-8418 | 563-853-2645 | |||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Mobilization | 1 | L.S. | $500.00 | $500.00 | $1,000.00 | $1,000.00 | $1,850.00 | $1,850.00 | ||||
| 2 | Revetment, 4 to 6 inch | 25 | Tons | $36.00 | $900.00 | $50.00 | $1,250.00 | $34.00 | $850.00 | ||||
| 3 | Grout Mix | 10 | C.Y. | $250.00 | $2,500.00 | $250.00 | $2,500.00 | $285.00 | $2,850.00 | ||||
| $3,900.00 | $4,750.00 | $5,550.00 | |||||||||||
4 | 5 | 6 | |||||||||||
| Estimated Cost: $5,000.00 | Contractor: | Tschigffrie Excavating Co | Hanson Construction LLC | Heim Concrete Construction | |||||||||
| Funding Source: 100% REAP Land Management, | 425 Julian Dubuque Dr PO Box 3280 | PO Box 614 | 2013 Dry Ridge Dr | ||||||||||
| Dubuque IA 52003 | Clear Lake IA 50428 | Lansing IA 52151 | |||||||||||
| Plan Sets Requested: 0 | Quantities | 563-557-7450 | 641-357-8171 | 563-586-2699 | |||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Mobilization | 1 | L.S. | $1,400.00 | $1,400.00 | $3,000.00 | $3,000.00 | $1,200.00 | $1,200.00 | ||||
| 2 | Revetment, 4 to 6 inch | 25 | Tons | $60.40 | $1,510.00 | $45.00 | $1,125.00 | $110.00 | $2,750.00 | ||||
| 3 | Grout Mix | 10 | C.Y. | $298.00 | $2,980.00 | $200.00 | $2,000.00 | $400.00 | $4,000.00 | ||||
| $5,890.00 | $6,125.00 | $7,950.00 | |||||||||||
7 | 8 | 9 | |||||||||||
| Estimated Cost: $5,000.00 | Contractor: | Connolly Construction Inc | |||||||||||
| Funding Source: 100% REAP Land Management, | 18409 N Cascade Rd PO Box 68 | ||||||||||||
| Peosta IA 52068 | |||||||||||||
| Plan Sets Requested: 0 | Quantities | 563-876-3225 | |||||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Mobilization | 1 | L.S. | $3,850.00 | $3,850.00 | $0.00 | $0.00 | ||||||
| 2 | Revetment, 4 to 6 inch | 25 | Tons | $57.00 | $1,425.00 | $0.00 | $0.00 | ||||||
| 3 | Grout Mix | 10 | C.Y. | $528.00 | $5,280.00 | $0.00 | $0.00 | ||||||
| $10,555.00 | $0.00 | $0.00 | |||||||||||
10/13/2026