| Bids For: | Location: | Brushy Creek SRA | Date: 7/15/2010 | Project No. |
| Utilities for - CXTShower BLD | County: | WEBSTER | Time: 3:00 p.m. | 10-02-94-01 |
1 | 2 | 3 | |||||||||||
| Estimated Cost: $36,517.00 | Contractor: | Hanson Construction | Schoon Construction Inc | C L Carroll Company Inc | |||||||||
| Funding Source: 100% I-JOBS, | PO Box 614 | 1500 S 2nd St | 3623 6th Ave | ||||||||||
| Clear Lake IA 50428 | Cherokee IA 51012 | Des Moines IA 50313 | |||||||||||
| Plan Sets Requested: 0 | Quantities | 641-357-8171 | 712-225-5736 | 515-282-7495 | |||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Mobilization | 1 | L.S. | $1,500.00 | $1,500.00 | $2,000.00 | $2,000.00 | $4,674.00 | $4,674.00 | ||||
| 2 | Earthfill needed | 53 | C.Y. | $25.00 | $1,325.00 | $26.00 | $1,378.00 | $12.00 | $636.00 | ||||
| 3 | Earthwork | 25 | C.Y. | $20.00 | $500.00 | $25.00 | $625.00 | $29.00 | $725.00 | ||||
| 4 | Road boring | 110 | L.F. | $3.00 | $330.00 | $12.00 | $1,320.00 | $54.00 | $5,940.00 | ||||
| 5 | PCC sidewalk 6" depth | 660 | S.F. | $5.50 | $3,630.00 | $6.18 | $4,078.80 | $9.00 | $5,940.00 | ||||
| 6 | Class "A" crushed stone | 190 | Tons | $25.00 | $4,750.00 | $25.90 | $4,921.00 | $16.00 | $3,040.00 | ||||
| 7 | 2" PVC SDR 35 septic pipe | 480 | L.F. | $4.50 | $2,160.00 | $9.63 | $4,622.40 | $19.00 | $9,120.00 | ||||
| 8 | Lift Station, installation | 1 | L.S. | $8,500.00 | $8,500.00 | $7,100.00 | $7,100.00 | $8,700.00 | $8,700.00 | ||||
| 9 | Connection to existing manhole | 1 | L.S. | $500.00 | $500.00 | $238.00 | $238.00 | $900.00 | $900.00 | ||||
| 10 | 2" HDPE water pipe | 595 | L.F. | $7.25 | $4,313.75 | $9.50 | $5,652.50 | $14.00 | $8,330.00 | ||||
| 11 | Connection to existing water | 1 | L.S. | $400.00 | $400.00 | $595.00 | $595.00 | $850.00 | $850.00 | ||||
| 12 | Water hydrant | 1 | Each | $225.00 | $225.00 | $980.00 | $980.00 | $2,600.00 | $2,600.00 | ||||
| 13 | Curb stop with box | 1 | Each | $375.00 | $375.00 | $580.00 | $580.00 | $525.00 | $525.00 | ||||
| 14 | Engineering fabric | 88 | S.F. | $3.00 | $264.00 | $0.50 | $44.00 | $2.00 | $176.00 | ||||
| 15 | #12 tracer wire | 600 | L.F. | $1.00 | $600.00 | $0.52 | $312.00 | $0.50 | $300.00 | ||||
| 16 | Tracer station | 1 | L.S. | $150.00 | $150.00 | $100.00 | $100.00 | $330.00 | $330.00 | ||||
| 17 | Shower stub-ups and & connection | 1 | L.S. | $750.00 | $750.00 | $2,700.00 | $2,700.00 | $5,700.00 | $5,700.00 | ||||
| 18 | 3/0 AWG cable | 40 | L.F. | $3.00 | $120.00 | $3.00 | $120.00 | $33.00 | $1,320.00 | ||||
| 19 | Trench | 30 | L.F. | $3.00 | $90.00 | $4.00 | $120.00 | $7.50 | $225.00 | ||||
| 20 | Connection to electric | 1 | L.S. | $450.00 | $450.00 | $3,000.00 | $3,000.00 | $1,600.00 | $1,600.00 | ||||
| $30,932.75 | $40,486.70 | $61,631.00 | |||||||||||