 Bids For:  Location:   Hayesville Bend WMA  Date: 2/16/2012  Project No.  
  Flood Damage Repairs  County:   KEOKUK  Time: 11:00 a.m.  09-05-54-01

 

 
1
2
3
Estimated Cost: $258,000.00
Contractor: 
Buehneman Inc.Cornerstone Excavating Inc.Sterk Excavating Inc
Funding Source: 90% Federal-FEMA 1, 10% Special Appropriations, 15808 - 232nd Street
212 South Marion Ave
117 - 180th Ave
Delta IA  52550Washington IA  52353Otley IA  50214
Plan Sets Requested: 15
Quantities
641-624-2001319-653-3957641-416-0110
No.Description:No.UnitUnit Price AmountUnit Price AmountUnit Price Amount
1Excavation, Dike Repair, In Place4584C.Y.$1.50$6,876.00 $2.95$13,522.80 $3.31$15,173.04 
2Excavation, Silt Removal3222C.Y.$1.50$4,833.00 $1.25$4,027.50 $0.89$2,867.58 
3Revetment, Class "D" Riprap4500Tons$24.69$111,105.00 $27.00$121,500.00 $28.20$126,900.00 
4Engineering Fabric5556S.Y.$0.91$5,055.96 $1.50$8,334.00 $0.90$5,000.40 
5Seeding, Fertilizing & Mulching1L.S.$300.00$300.00 $1,500.00$1,500.00 $2,512.00$2,512.00 
      $128,169.96  $148,884.30  $152,453.02 
Alternate        
6Excavation, Structural300C.Y.$3.33$999.00 $1.95$585.00 $3.14$942.00 
Alternate        
7Water Control Structure, Complete1L.S.$11,349.60$11,349.60 $16,000.00$16,000.00 $15,130.80$15,130.80 
Alternate        
8Bedding, Class "A" Cr. Stone52Tons$12.00$624.00 $18.00$936.00 $16.60$863.20 
      $141,142.56  $166,405.30  $169,389.02 
 
 
4
5
6
Estimated Cost: $258,000.00
Contractor: 
Hammes Buldozing Inc.Buford Dozing & Excavating LLCCole Construction Company Inc
Funding Source: 90% Federal-FEMA 1, 10% Special Appropriations, 16520 Hwy 92
29623 - 260th St
24100 Queen Ave
Sigourney IA  52591Bonaparte IA  52620Keosauqua IA  525658329
Plan Sets Requested: 15
Quantities
641-660-1610319480-1492319-592-3103
No.Description:No.UnitUnit Price AmountUnit Price AmountUnit Price Amount
1Excavation, Dike Repair, In Place4584C.Y.$1.40$6,417.60 $2.15$9,855.60 $1.98$9,076.32 
2Excavation, Silt Removal3222C.Y.$2.25$7,249.50 $2.19$7,056.18 $1.56$5,026.32 
3Revetment, Class "D" Riprap4500Tons$29.00$130,500.00 $27.50$123,750.00 $29.50$132,750.00 
4Engineering Fabric5556S.Y.$1.35$7,500.60 $1.50$8,334.00 $1.50$8,334.00 
5Seeding, Fertilizing & Mulching1L.S.$5,500.00$5,500.00 $5,000.00$5,000.00 $3,000.00$3,000.00 
Alternate        
6Excavation, Structural300C.Y.$2.00$600.00 $2.10$630.00 $3.50$1,050.00 
Alternate        
7Water Control Structure, Complete1L.S.$15,000.00$15,000.00 $23,220.00$23,220.00 $22,050.00$22,050.00 
Alternate        
8Bedding, Class "A" Cr. Stone52Tons$21.00$1,092.00 $19.20$998.40 $22.50$1,170.00 
      $173,859.70  $178,844.18  $182,456.64 
 
7
8
9
Estimated Cost: $258,000.00
Contractor: 
Drish Construction IncTK Concrete IncDeLong Construction Inc
Funding Source: 90% Federal-FEMA 1, 10% Special Appropriations, 1701 S Main
1608 Fifield Rd
PO Box 111
PO Box 488
Fairfield IA  52556Pella IA  50219Washington IA  52353
Plan Sets Requested: 15
Quantities
641-472-9506641-628-4590319-653-3334
No.Description:No.UnitUnit Price AmountUnit Price AmountUnit Price Amount
1Excavation, Dike Repair, In Place4584C.Y.$2.00$9,168.00 $6.50$29,796.00 $2.70$12,376.80 
2Excavation, Silt Removal3222C.Y.$1.50$4,833.00 $1.50$4,833.00 $2.70$8,699.40 
3Revetment, Class "D" Riprap4500Tons$27.50$123,750.00 $27.00$121,500.00 $28.50$128,250.00 
4Engineering Fabric5556S.Y.$1.88$10,445.28 $1.00$5,556.00 $1.60$8,889.60 
5Seeding, Fertilizing & Mulching1L.S.$2,000.00$2,000.00 $5,000.00$5,000.00 $5,000.00$5,000.00 
Alternate        
6Excavation, Structural300C.Y.$6.00$1,800.00 $4.00$1,200.00 $5.00$1,500.00 
Alternate        
7Water Control Structure, Complete1L.S.$37,500.00$37,500.00 $27,500.00$27,500.00 $31,500.00$31,500.00 
Alternate        
8Bedding, Class "A" Cr. Stone52Tons$29.45$1,531.40 $20.00$1,040.00 $19.80$1,029.60 
      $191,027.68  $196,425.00  $197,245.40 
 
 
10
11
12
Estimated Cost: $258,000.00
Contractor: 
Kevin Kent ConstructionSeaton ConstructionConnolly Construction Inc
Funding Source: 90% Federal-FEMA 1, 10% Special Appropriations, 15157 US Hwy 34
602 Locust St
PO Box 213
18409 N Cascade Rd
PO Box 68
Lucas IA  50151Deep River IA  522220213Peosta IA  52068
Plan Sets Requested: 15
Quantities
641-766-61266415952261563-876-3225
No.Description:No.UnitUnit Price AmountUnit Price AmountUnit Price Amount
1Excavation, Dike Repair, In Place4584C.Y.$4.25$19,482.00 $3.00$13,752.00 $8.25$37,818.00 
2Excavation, Silt Removal3222C.Y.$3.25$10,471.50 $3.75$12,082.50 $11.60$37,375.20 
3Revetment, Class "D" Riprap4500Tons$28.75$129,375.00 $32.25$145,125.00 $25.65$115,425.00 
4Engineering Fabric5556S.Y.$1.90$10,556.40 $2.50$13,890.00 $1.55$8,611.80 
5Seeding, Fertilizing & Mulching1L.S.$12,000.00$12,000.00 $14,500.00$14,500.00 $7,000.00$7,000.00 
Alternate        
6Excavation, Structural300C.Y.$6.00$1,800.00 $6.00$1,800.00 $9.35$2,805.00 
Alternate        
7Water Control Structure, Complete1L.S.$18,500.00$18,500.00 $32,050.00$32,050.00 $50,000.00$50,000.00 
Alternate        
8Bedding, Class "A" Cr. Stone52Tons$18.00$936.00 $19.50$1,014.00 $22.70$1,180.40 
      $203,120.90  $234,213.50  $260,215.40 
 
13
14
15
Estimated Cost: $258,000.00
Contractor: 
Merryman Excavation Inc.Ag & Turf Construction LLC
Funding Source: 90% Federal-FEMA 1, 10% Special Appropriations, 1501 Lamb Rd
17520 110th Ave

Woodstock IL  60098Davenport IA  52804  
Plan Sets Requested: 15
Quantities
815-337-1700563-349-2089
No.Description:No.UnitUnit Price AmountUnit Price AmountUnit Price Amount
1Excavation, Dike Repair, In Place4584C.Y.$6.35$29,108.40 $3.00$13,752.00 $0.00 
2Excavation, Silt Removal3222C.Y.$3.75$12,082.50 $4.00$12,888.00 $0.00 
3Revetment, Class "D" Riprap4500Tons$37.65$169,425.00 $40.00$180,000.00 $0.00 
4Engineering Fabric5556S.Y.$1.35$7,500.60 $2.00$11,112.00 $0.00 
5Seeding, Fertilizing & Mulching1L.S.$11,625.00$11,625.00 $6,000.00$6,000.00 $0.00 
Alternate        
6Excavation, Structural300C.Y.$6.30$1,890.00 $550.00$165,000.00 $0.00 
Alternate        
7Water Control Structure, Complete1L.S.$40,360.00$40,360.00 $45,000.00$45,000.00 $0.00 
Alternate        
8Bedding, Class "A" Cr. Stone52Tons$31.65$1,645.80 $25.00$1,300.00 $0.00 
      $273,637.30  $435,052.00  $0.00 
 



 