IOWA DEPARTMENT OF NATURAL RESOURCES
ENGINEERING BUREAU

INFORMAL BID TAB
NOTICE: This document represents bids that were opened on the letting date and may be subject to further review. This is not the official bid tab.

 Bids For:  Location:   Riverton Wildlife Area  Date: 2/17/2011  Project No.  
  Repair flood damage to road  County:   FREMONT  Time: 11:00 a.m.  10-04-36-02

 

 
1
2
3
Estimated Cost: $850,000.00
Contractor: 
Concrete Technologies IncGodbersen Smith Construction Co IncALLIED MANATTS GROUP LLC
Funding Source: 90% Federal-FEMA 1, 10% Park & Institutional Road Fund, 3809 NW 109th St Suite D
5784 State Hwy 175
PO Box 33
PO Box 687
Urbandale IA  50322Ida Grove IA  51445Charles City IA  50616
Plan Sets Requested: 18
Quantities
515-252-1650712-364-3388641-228-4256
No.Description:No.UnitUnit Price AmountUnit Price AmountUnit Price Amount
1Special Backfill6577Tons$8.50$55,904.50 $10.75$70,702.75 $9.00$59,193.00 
2Excavation, Class 10 Roadway & Borrow22422C.Y.$2.30$51,570.60 $2.25$50,449.50 $2.25$50,449.50 
3Shoulder Construction, Earth145.1STA.$49.50$7,182.45 $50.00$7,255.00 $48.50$7,037.35 
4Std. or Slip Form PCC Pavement, Cl. "C", Cl.2 Dur., 6"17399S.Y.$22.00$382,778.00 $24.75$430,625.25 $24.25$421,925.75 
5Removal and Crushing of Pavement12679S.Y.$4.25$53,885.75 $3.30$41,840.70 $4.20$53,251.80 
6Traffic Control1L.S.$2,050.00$2,050.00 $3,000.00$3,000.00 $2,000.00$2,000.00 
7Mobilization1L.S.$52,000.00$52,000.00 $35,000.00$35,000.00 $58,000.00$58,000.00 
8Seeding and Fertilizing (Rural)18.5Acres$845.00$15,632.50 $830.00$15,355.00 $830.00$15,355.00 
9Silt Fence14900L.F.$1.40$20,860.00 $1.38$20,562.00 $1.38$20,562.00 
10Removal of Silt Fence14900L.F.$0.02$298.00 $0.02$298.00 $0.02$298.00 
11Construction Survey1L.S.$5,100.00$5,100.00 $6,000.00$6,000.00 $5,000.00$5,000.00 
      $647,261.80  $681,088.20  $693,072.40 
 
 
4
5
6
Estimated Cost: $850,000.00
Contractor: 
Bluffs Paving & Utility, IncCedar Valley CorpLamb Tiling
Funding Source: 90% Federal-FEMA 1, 10% Park & Institutional Road Fund, 20474 Monument Road
2637 Wagner Rd
2751 Marion Ave
Crescent IA  51526Waterloo IA  50703Greenfield IA  50849
Plan Sets Requested: 18
Quantities
712-328-0068319-235-9537641-743-8312
No.Description:No.UnitUnit Price AmountUnit Price AmountUnit Price Amount
1Special Backfill6577Tons$17.14$112,729.78 $9.10$59,850.70 $15.10$99,312.70 
2Excavation, Class 10 Roadway & Borrow22422C.Y.$3.00$67,266.00 $2.25$50,449.50 $3.10$69,508.20 
3Shoulder Construction, Earth145.1STA.$160.00$23,216.00 $48.50$7,037.35 $60.00$8,706.00 
4Std. or Slip Form PCC Pavement, Cl. "C", Cl.2 Dur., 6"17399S.Y.$22.50$391,477.50 $25.17$437,932.83 $24.75$430,625.25 
5Removal and Crushing of Pavement12679S.Y.$1.36$17,243.44 $4.20$53,251.80 $2.35$29,795.65 
6Traffic Control1L.S.$2,000.00$2,000.00 $2,000.00$2,000.00 $15,000.00$15,000.00 
7Mobilization1L.S.$39,934.00$39,934.00 $65,000.00$65,000.00 $16,500.00$16,500.00 
8Seeding and Fertilizing (Rural)18.5Acres$830.00$15,355.00 $790.00$14,615.00 $840.00$15,540.00 
9Silt Fence14900L.F.$1.38$20,562.00 $1.50$22,350.00 $1.45$21,605.00 
10Removal of Silt Fence14900L.F.$0.02$298.00 $0.01$149.00 $0.50$7,450.00 
11Construction Survey1L.S.$6,200.00$6,200.00 $5,500.00$5,500.00 $7,500.00$7,500.00 
      $696,281.72  $718,136.18  $721,542.80 
 
7
8
9
Estimated Cost: $850,000.00
Contractor: 
Carley Construction LLCTab ConstructionTCW Construction Inc
Funding Source: 90% Federal-FEMA 1, 10% Park & Institutional Road Fund, 216 MEADOW DR
4153 S 67th St
141 M Street
TREYNOR IA  51575Omaha NE  68117Lincoln NE  68508
Plan Sets Requested: 18
Quantities
712-487-3599402-331-1244402-475-5030
No.Description:No.UnitUnit Price AmountUnit Price AmountUnit Price Amount
1Special Backfill6577Tons$13.65$89,776.05 $19.70$129,566.90 $12.90$84,843.30 
2Excavation, Class 10 Roadway & Borrow22422C.Y.$4.56$102,244.32 $3.51$78,701.22 $2.70$60,539.40 
3Shoulder Construction, Earth145.1STA.$56.00$8,125.60 $52.00$7,545.20 $58.40$8,473.84 
4Std. or Slip Form PCC Pavement, Cl. "C", Cl.2 Dur., 6"17399S.Y.$24.50$426,275.50 $21.40$372,338.60 $28.30$492,391.70 
5Removal and Crushing of Pavement12679S.Y.$2.62$33,218.98 $3.78$47,926.62 $5.05$64,028.95 
6Traffic Control1L.S.$700.00$700.00 $2,100.00$2,100.00 $5,500.00$5,500.00 
7Mobilization1L.S.$30,000.00$30,000.00 $51,217.00$51,217.00 $63,500.00$63,500.00 
8Seeding and Fertilizing (Rural)18.5Acres$871.00$16,113.50 $855.00$15,817.50 $1,000.00$18,500.00 
9Silt Fence14900L.F.$1.45$21,605.00 $1.50$22,350.00 $1.65$24,585.00 
10Removal of Silt Fence14900L.F.$0.03$447.00 $0.01$149.00 $0.05$745.00 
11Construction Survey1L.S.$5,250.00$5,250.00 $7,930.00$7,930.00 $0.00$0.00 
      $733,755.95  $735,642.04  $823,107.19 
 
 
10
11
12
Estimated Cost: $850,000.00
Contractor: 
KP Construction Inc.Whitehead Farms Construction Inc
Funding Source: 90% Federal-FEMA 1, 10% Park & Institutional Road Fund, 1624 210th Street
2468 300th Ave

Sergeant Bluff IA  51054Sidney IA  51652  
Plan Sets Requested: 18
Quantities
712-943-4355712-374-3232
No.Description:No.UnitUnit Price AmountUnit Price AmountUnit Price Amount
1Special Backfill6577Tons$15.00$98,655.00 $20.00$131,540.00 $0.00 
2Excavation, Class 10 Roadway & Borrow22422C.Y.$5.00$112,110.00 $5.41$121,303.02 $0.00 
3Shoulder Construction, Earth145.1STA.$230.00$33,373.00 $172.29$24,999.279 $0.00 
4Std. or Slip Form PCC Pavement, Cl. "C", Cl.2 Dur., 6"17399S.Y.$28.00$487,172.00 $33.34$580,082.66 $0.00 
5Removal and Crushing of Pavement12679S.Y.$3.50$44,376.50 $4.55$57,689.45 $0.00 
6Traffic Control1L.S.$3,000.00$3,000.00 $2,000.00$2,000.00 $0.00 
7Mobilization1L.S.$30,000.00$30,000.00 $5,000.00$5,000.00 $0.00 
8Seeding and Fertilizing (Rural)18.5Acres$800.00$14,800.00 $432.43$7,999.955 $0.00 
9Silt Fence14900L.F.$1.50$22,350.00 $1.50$22,350.00 $0.00 
10Removal of Silt Fence14900L.F.$1.00$14,900.00 $0.10$1,490.00 $0.00 
11Construction Survey1L.S.$14,000.00$14,000.00 $2,000.00$2,000.00 $0.00 
      $874,736.50  $956,454.364  $0.00 
 



 

10/13/2026