IOWA DEPARTMENT OF NATURAL RESOURCES |
|
| Bids For: | Location: | Big Spring Hatchery | Date: 2/17/2011 | Project No. |
| Office/Visitor Building | County: | CLAYTON | Time: 11:00 a.m. | 09-03-22-03 |
1 | 2 | 3 | |||||||||||
| Estimated Cost: $1,000,000.00 | Contractor: | Cresco Building Service, Inc. | Loecke Building Service | Tricon General Construction | |||||||||
| Funding Source: 50% REAP OS Acquisition & Development, 50% F&W Trust-Fisheries Non-Habitat Stamp, | 521 2nd Avenue SW | 1501 210th St | 2245 Kerper Blvd, Suite #2 | ||||||||||
| Cresco IA 52136 | Manchester IA 52057 | Dubuque IA 52001 | |||||||||||
| Plan Sets Requested: 20 | Quantities | 563-547-2525 | (563) 927-5677 | 563.588.9516 | |||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Maintenance Building Construction | 1 | L.S. | $724,518.00 | $724,518.00 | $759,000.00 | $759,000.00 | $775,000.00 | $775,000.00 | ||||
| 2 | Excavation of Unsuitable Material | 2325 | C.Y. | $13.00 | $30,225.00 | $12.50 | $29,062.50 | $10.00 | $23,250.00 | ||||
| 3 | Sheet Vinyl Allowance | 1 | L.S. | $704.00 | $704.00 | $720.00 | $720.00 | $736.00 | $736.00 | ||||
| 4 | Carpet Tile Allowance | 1 | L.S. | $2,720.00 | $2,720.00 | $3,040.00 | $3,040.00 | $3,040.00 | $3,040.00 | ||||
| $758,167.00 | $791,822.50 | $802,026.00 | |||||||||||
| Alternate | |||||||||||||
| 5 | Front Entrance Canopy | 1 | L.S. | $18,127.00 | $18,127.00 | $16,700.00 | $16,700.00 | $27,000.00 | $27,000.00 | ||||
| Alternate | |||||||||||||
| 6 | Observation Deck | 1 | L.S. | $29,915.00 | $29,915.00 | $37,215.00 | $37,215.00 | $35,000.00 | $35,000.00 | ||||
| Alternate | |||||||||||||
| 7 | PCC Drive & Parking Lot | 1 | L.S. | $38,445.00 | $38,445.00 | $45,900.00 | $45,900.00 | $33,000.00 | $33,000.00 | ||||
| $844,654.00 | $891,637.50 | $897,026.00 | |||||||||||
4 | 5 | 6 | |||||||||||
| Estimated Cost: $1,000,000.00 | Contractor: | Olympic Builders General Contractors, Inc | Matt Construction Inc | David Finholt Construction Inc. | |||||||||
| Funding Source: 50% REAP OS Acquisition & Development, 50% F&W Trust-Fisheries Non-Habitat Stamp, | 405 North Star Road | 203 Y Ave | 1813 Trout Run Road | ||||||||||
| Holmen WI 54636 | Sumner IA 50674 | Decorah IA 52101 | |||||||||||
| Plan Sets Requested: 20 | Quantities | 608.526.4622 | 563-578-8418 | 563.382.9360 | |||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Maintenance Building Construction | 1 | L.S. | $795,328.00 | $795,328.00 | $792,754.00 | $792,754.00 | $809,151.50 | $809,151.50 | ||||
| 2 | Excavation of Unsuitable Material | 2325 | C.Y. | $14.00 | $32,550.00 | $15.00 | $34,875.00 | $12.50 | $29,062.50 | ||||
| 3 | Sheet Vinyl Allowance | 1 | L.S. | $768.00 | $768.00 | $832.00 | $832.00 | $800.00 | $800.00 | ||||
| 4 | Carpet Tile Allowance | 1 | L.S. | $2,784.00 | $2,784.00 | $2,848.00 | $2,848.00 | $2,720.00 | $2,720.00 | ||||
| Alternate | |||||||||||||
| 5 | Front Entrance Canopy | 1 | L.S. | $16,840.00 | $16,840.00 | $19,000.00 | $19,000.00 | $19,255.00 | $19,255.00 | ||||
| Alternate | |||||||||||||
| 6 | Observation Deck | 1 | L.S. | $26,520.00 | $26,520.00 | $33,000.00 | $33,000.00 | $28,928.00 | $28,928.00 | ||||
| Alternate | |||||||||||||
| 7 | PCC Drive & Parking Lot | 1 | L.S. | $41,000.00 | $41,000.00 | $41,000.00 | $41,000.00 | $38,986.00 | $38,986.00 | ||||
| $915,790.00 | $924,309.00 | $928,903.00 | |||||||||||
7 | 8 | 9 | |||||||||||
| Estimated Cost: $1,000,000.00 | Contractor: | Porter & Porter Construction LLC | Larson Contracting Central LLC | Portzen Construction | |||||||||
| Funding Source: 50% REAP OS Acquisition & Development, 50% F&W Trust-Fisheries Non-Habitat Stamp, | 1728 Grant Avenue | P.O. Box 7 | 205 Stone Valley Dr | ||||||||||
| Independence IA 50644 | Lake Mills IA 50450 | Dubuque IA 52003 | |||||||||||
| Plan Sets Requested: 20 | Quantities | 319-334-4861 | 641.592.5800 | 563-557-7642 | |||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Maintenance Building Construction | 1 | L.S. | $819,000.00 | $819,000.00 | $842,639.00 | $842,639.00 | $865,500.00 | $865,500.00 | ||||
| 2 | Excavation of Unsuitable Material | 2325 | C.Y. | $10.00 | $23,250.00 | $13.00 | $30,225.00 | $22.00 | $51,150.00 | ||||
| 3 | Sheet Vinyl Allowance | 1 | L.S. | $736.00 | $736.00 | $0.00 | $0.00 | $736.00 | $736.00 | ||||
| 4 | Carpet Tile Allowance | 1 | L.S. | $2,880.00 | $2,880.00 | $2,560.00 | $2,560.00 | $3,040.00 | $3,040.00 | ||||
| Alternate | |||||||||||||
| 5 | Front Entrance Canopy | 1 | L.S. | $26,000.00 | $26,000.00 | $16,275.00 | $16,275.00 | $27,000.00 | $27,000.00 | ||||
| Alternate | |||||||||||||
| 6 | Observation Deck | 1 | L.S. | $24,000.00 | $24,000.00 | $24,265.00 | $24,265.00 | $27,000.00 | $27,000.00 | ||||
| Alternate | |||||||||||||
| 7 | PCC Drive & Parking Lot | 1 | L.S. | $39,000.00 | $39,000.00 | $38,408.00 | $38,408.00 | $37,500.00 | $37,500.00 | ||||
| $934,866.00 | $954,372.00 | $1,011,926.00 | |||||||||||
10 | 11 | 12 | |||||||||||
| Estimated Cost: $1,000,000.00 | Contractor: | Vieco Dev. & Construction Co. Inc. | |||||||||||
| Funding Source: 50% REAP OS Acquisition & Development, 50% F&W Trust-Fisheries Non-Habitat Stamp, | 941 25th Avenue #200 PO Box 8022 | ||||||||||||
| Coralville IA 52241 | |||||||||||||
| Plan Sets Requested: 20 | Quantities | 816-232-9044 | |||||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Maintenance Building Construction | 1 | L.S. | $1,053,171.50 | $1,053,171.50 | $0.00 | $0.00 | ||||||
| 2 | Excavation of Unsuitable Material | 2325 | C.Y. | $6.50 | $15,112.50 | $0.00 | $0.00 | ||||||
| 3 | Sheet Vinyl Allowance | 1 | L.S. | $736.00 | $736.00 | $0.00 | $0.00 | ||||||
| 4 | Carpet Tile Allowance | 1 | L.S. | $3,040.00 | $3,040.00 | $0.00 | $0.00 | ||||||
| Alternate | |||||||||||||
| 5 | Front Entrance Canopy | 1 | L.S. | $23,800.00 | $23,800.00 | $0.00 | $0.00 | ||||||
| Alternate | |||||||||||||
| 6 | Observation Deck | 1 | L.S. | $46,600.00 | $46,600.00 | $0.00 | $0.00 | ||||||
| Alternate | |||||||||||||
| 7 | PCC Drive & Parking Lot | 1 | L.S. | $44,275.00 | $44,275.00 | $0.00 | $0.00 | ||||||
| $1,186,735.00 | $0.00 | $0.00 | |||||||||||
10/13/2026