PROJECTS LETTING -  April , 2020

 
 
bid envelopes

 
 

The following projects are currently advertised for bids. Interested bidders may find general information about each project, as well as printable actual Contract Documents in PDF format. The general information is the same project description provided to Newspapers and by direct mail solicitations. The Contract Documents include the Drawings and the entire Project Manual.  Drawings can be printed on any regular or large format printers. The Project Manual includes Proposal Forms,  Front End Documents, General and Supplementary Covenants, and Technical specifications. All these are also completely printable.

Effective October 2009, the Department will no longer be responsible for providing hard copy notice to bidders or addenda to either contractors or plan rooms. An email listserv has been created to communicate electronically with vendors currently on file with the DNR. As a member of this listserv, you will receive electronic notice to bidder information on a regular basis. To subscribe to this list, click here.

The Department will be utilizing the vendor Beeline and Blue to provide printed copies of Plans and Specifications and Addenda upon request. The department will no longer provide complimentary copies of Plans and Specifications to contractors or sub-contractors after award of the contract. Please visit dfs.beelineandblue.com/iowa or contact (515) 244-1611 for more information.

To access any of these, unless you have already done so, you will need to download and install Acrobat Reader from the Adobe Website. 
You may obtain a free download from
 

Click on the project names below to view the one(s) which interest you.

MONTGOMERY 20-04-69-03 Viking Lake - Pond Repair-2020-04-09   Bid Completion detail
DELAWARE 20-03-28-05 Backbone State Park - Beach Lodge Lighting-2020-04-16   Bid Completion detail
DELAWARE 20-03-28-06 Backbone State Park - Cabin Flooring-2020-04-16   Bid Completion detail
DICKINSON 20-01-30-16 Emerson Bay and Hattie Elston Ramps - Courtesy Docks-2020-04-16   Bid Completion detail
DICKINSON 16-01-30-08 Great Lakes Wildlife Unit - Garlock Slough Small Wetland RT-2020-04-16   Bid Completion detail
HARDIN 19-02-42-01 Pine Lake State Park - Shower Buildings & Cabin Renovations-2020-04-16   Bid Completion detail
HARDIN 19-02-42-01 Pine Lake State Park - Shower Buildings & Cabin Renovations CONTRACT-2020-04-16   Bid Completion detail
JONES 18-06-53-01 Indian Bluffs WMA - Road Maintenance-2020-04-16   Bid Completion detail
MONTGOMERY 19-04-69-05 Viking Lake - building demo @ Aldersgate Rebid-2020-04-16   Bid Completion detail
VAN BUREN 21-06-89-01 Lake Sugema - Fishing Pier Deck-2020-04-30   Bid Completion detail
WARREN 20-05-91-03 Banner Lakes At Summerset State Park - Flood Damage Repairs-2020-04-30   Bid Completion detail
WARREN 20-05-91-02 Lake Ahquabi State Park - CCC Bridge Abutment Repair-2020-04-30   Bid Completion detail




DICKINSON -- PROJECT # 20-01-30-16                4/16/2020                Large Project Letting
EMERSON BAY AND HATTIE ELSTON RAMPS
COURTESY DOCKS
Proposal Guarantee: $6,250
Completion Date: 7/22/2020

   This project consists of removing the existing courtesy docks and installing commercial floating courtesy docks with concrete decking, gangways, placing concrete between boat ramps at site 1, and incidental work as directed by DNR inspector.

ESTIMATED QUANTITIES:
    COMMERCIAL FLOATING DOCK - CONCRETE DECK 8FT X 40FT W/GANGWAY     2 Each
    COMMERCIAL FLOATING DOCK - CONCRETE DECK 8FT X 60FT W/GANGWAY     1 Each
    REINFORCED CONCRETE, 6" DEPTH, CLASS 'C'     53 S.Y.
    Class A Crushed Stone     17 Tons

notice to bidders

download plans and specs

Plans can be ordered by following this link: http://bit.ly/IADNRPlans

planholders list




HARDIN -- PROJECT # 19-02-42-01                4/16/2020                Large Project Letting
PINE LAKE STATE PARK
SHOWER BUILDINGS & CABIN RENOVATIONS
Proposal Guarantee: $62,500
Completion Date: 4/30/2021

   Pine Lake State Park is located just North East of Eldora, Iowa. The park will receive a new host, full hook-up camp site, two (2) new shower buildings, a new pit latrine, a new slab on the Center Point shelter, and interior renovations in the four (4) cabins. As an alternate, a new Design Guide shelter and demo of the original shelter. Also, the contractor shall demolish the existing shower/restroom buildings and miscellaneous other items as shown in the drawings.

ESTIMATED QUANTITIES:
    DEMOLITION & SALVAGE     1 L.S.
    TREE CLEARING AND GRUBBING     1 L.S.
    GRADING     1 L.S.
    SEEDING, FERTILIZING, AND MULCHING     1 L.S.
    CLASS "A" CRUSHED STONE     10 Tons
    SANITARY SEWER SERVICE (SHOWER BUILDINGS & CAMP HOST SITE)     1 L.S.
    SANITARY MANHOLE FOR SHOWER BUILDINGS     2 Each
    DOMESTIC WATER LINES TO SHOWER BUILDINGS     1 L.S.
    DRAIN DOWN WATER PIT     2 Each
    SITE ELECTRICAL SERVICE     1 L.S.
    CONCRETE PARKING, SIDEWALKS, & STOOP FOOTINGS     1 L.S.
    SHOWER BUILDING (NORWAY PINE - ALL ITEMS INCLUSIVE)     1 L.S.
    FAMILY SHOWER BUILDING (JUNIPER - ALL ITEMS INCLUSIVE)     1 L.S.
    PIT LATRINE BUILDING (ALL ITEMS INCLUSIVE)     1 L.S.
    CABIN RENOVATIONS (FOUR (4) CABINS ALL ITEMS INCLUSIVE)     1 L.S.
    CAMP HOST SITE (ALL ITEMS INCLUSIVE)     1 L.S.
    CONSTRUCTION STAKING     1 L.S.
    MOBILIZATION     1 L.S.
Alternate
    ALTERNATE #1: NEW SHELTER CONSTRUCTION (ALL ITEMS INCLUSIVE)     1 L.S.
Alternate
    ALTERNATE #2: EXISTING SHELTER SLAB REPLACEMENT AND SIDEWALK     1 L.S.

notice to bidders

download plans and specs

Plans can be ordered by following this link: http://bit.ly/IADNRPlans

planholders list




JONES -- PROJECT # 18-06-53-01                4/16/2020                Large Project Letting
INDIAN BLUFFS WMA
ROAD MAINTENANCE
Proposal Guarantee: $12,500
Completion Date: 10/31/2020

   This project consists of granular roadway maintenance - clearing/grubbing, reshaping/cleaning ditches, roadway realignment, ditch check construction, culvert cleaning, blading/shaping and spreading new rock.

ESTIMATED QUANTITIES:
    2101 - CLEARING/GRUBBING     1 L.S.
    2102 - EXCAVATION, CL 10, RDWY+BORROW     35 C.Y.
    2102 - EXCAVATION, CL 12, BOULDER/ROCK FRAGMENT     72 C.Y.
    2125 - RESHAPING/CLEANING DITCHES     35.7 STA.
    2127 - RECONSTRUCTION OF ROADBED - BLADING/SHAPING     29.5 STA.
    2127 - RECONSTRUCTION OF ROADBED - MOVING ROAD     6.2 STA.
    2312 - GRANULAR SURFACING ON ROAD, CLASS A CRUSHED STONE     1,363 Tons
    2312 - GRANULAR SURFACING ON ROAD, MACADAM STONE     210 Tons
    2507 - EROSION STONE - DITCH CHECKS     119 Tons
    2507 - EROSION STONE - OUTLETS     30 Tons
    2518 - SAFETY CLOSURE     2 Each
    2533 - MOBILIZATION     1 L.S.
    2601 - STABILIZE CROP - SEED+FERTILIZE     2.4 Acres

notice to bidders

download plans and specs

Plans can be ordered by following this link: http://bit.ly/IADNRPlans

planholders list




MONTGOMERY -- PROJECT # 20-04-69-03                4/9/2020                Small Project Letting
VIKING LAKE
POND REPAIR
Proposal Guarantee: $0
Completion Date: 9/30/2020

   This project is designed to repair a pond dike at the Aldersgate Camp at Viking Lake State Park. Brush removal is required on the pond dike and brush will be piled north of the borrow area. Fill material to fix the washout in the dike shall come from the borrow area on the NW side of dike, below existing trail. The new 8" diameter smooth metal pipe shall have 2 anti-seep colars installed as shown on the drawing. The new 8"diameter pipe shall have a canopy inlet installed on the pipe. The canopy inlet shall be incidental to the new pipe and not paid separately. Reshaping the washed out area on the outlet of the emergency spillway is required and this shall be incidental to the earthwork item and not paid separately. Site restoration is required for all disturbed areas including the access trail. Seed as per spec 02930.

Contact:
Mark Johnson
515-250-3713
mark.johnson@dnr.iowa.gov




DELAWARE -- PROJECT # 20-03-28-05                4/16/2020                Small Project Letting
BACKBONE STATE PARK
BEACH LODGE LIGHTING
Proposal Guarantee: $0
Completion Date: 6/30/2020

   Backbone State Park has a Beach Lodge which has poor lighting. This project will remove the existing lighting in the two assembly rooms in the Beach Lodge and install new chandelier fixtures and can lights throughout the two spaces. Proposal and plan may be obtained by emailing name, address, and phone number to melvin.pacovsky@dnr.iowa.gov

Contact:
Mel Pacovsky
319-240-3553
melvin.pacovsky@dnr.iowa.gov




DELAWARE -- PROJECT # 20-03-28-06                4/16/2020                Small Project Letting
BACKBONE STATE PARK
CABIN FLOORING
Proposal Guarantee: $0
Completion Date: 8/14/2020

   This project can begin construction & demolition July 10, 2020 and shall be completed no later than August 14, 2020. Contractor shall move all furniture to a safe location within the cabin and protect in place. Contractor shall then remove all trim, toe-kicks, thresholds, and flooring finishes and underlayment in cabins 9 - 12 (4 similar cabins total) except the main-level restrooms, lower-level mechanical rooms, and cabin #10 entry area. After removal of flooring and prep for new floor, contractor shall install new flooring according to finish floor plans sheet A-100. Rough dimensions are provided but verification of accuracy shall be the contractor's liability. Vinyl shall be installed in the entry way, restrooms and kitchen area shown, the vinyl shall be Armstrong Stratamax - Ambleside vinyl, fully-adhered, or State of Iowa approved equivalent. The carpet shall be in all of the bedrooms and living rooms as shown on sheet A-100. The carpet shall be Shaw 18x36 Quartz 5T017 carpet squares, color to be 14740 - Zircon, or State of Iowa approved equivalent. The tiles shall be installed with carpet tile adhesive. Contractor to provide four (4) full boxes of extra tiles to the Parks staff. Contractor shall provide all transition, termination bars, and adapter strips as needed, existing accessory hardware is to be disposed. Once all flooring is installed and replaced, contractor shall install trim, toe-kicks, and thresholds. Contractor shall thoroughly clean the cabins and return all furniture to the original location. Proposal may be obtained by emailing melvin.pacovsky@dnr.iowa.gov your name, address, and phone number.

Contact:
Mel Pacovsky
319-240-3553
melvin.pacovsky@dnr.iowa.gov




DICKINSON -- PROJECT # 16-01-30-08                4/16/2020                Small Project Letting
GREAT LAKES WILDLIFE UNIT
GARLOCK SLOUGH SMALL WETLAND RT
Proposal Guarantee: $0
Completion Date: 9/11/2020

   This project is designed to enhance three wetland pool elements on the Garlock Slough Wildlife Management Area (WMA), Dickinson County, Iowa. Work under this project includes earthfill (dike construction), excavation (channel & shallow water), tile investigation, tile breaks, tile installation (outlet construction), and a small amount of erosion stone.

Contact:
Jeff Felts
515-250-3712
Jeff.Felts@dnr.iowa.gov




MONTGOMERY -- PROJECT # 19-04-69-05                4/16/2020                Small Project Letting
VIKING LAKE
BUILDING DEMO @ ALDERSGATE REBID
Proposal Guarantee: $0
Completion Date: 9/30/2020

   Building #1 - Dorm Building 64'x36' with 16'x64' wooden deck to north, includes 17'x17' concrete patio on west side and all sidewalks. Building #2 - Shower Building 16'8"x16'8", includes outside concrete at doorways. Building #3 - Dinning Hall/Office Building 120'x50', includes sidewalks, retaining walls and cooler. Disconnect power for all buildings at the meter/disconnect for the building and remove all wiring to the buildings. Disconnect and cap waterline for all buildings at the outside valve and remove all piping to the buildings. Cap all sewer lines 10' from buildings and remove all piping to the buildings. Mark all capped sewer lines and water valves with a steel "T" post for future reference. Shape all building sites to drain after buildings and concrete is removed from site and seed as per spec 02930.

Contact:
Mark Johnson
515-250-3713
mark.johnson@dnr.iowa.gov




VAN BUREN -- PROJECT # 21-06-89-01                4/30/2020                Small Project Letting
LAKE SUGEMA
FISHING PIER DECK
Proposal Guarantee:
Completion Date: 7/31/2020

   Project includes replacement of treated wood decking on a fishing pier on Lake Sugema.

Contact:
Michael Dufoe
515-985-9196
Michael.dufoe@dnr.iowa.gov




WARREN -- PROJECT # 20-05-91-03                4/30/2020                Small Project Letting
BANNER LAKES AT SUMMERSET STATE PARK
FLOOD DAMAGE REPAIRS
Proposal Guarantee: $0
Completion Date: 8/31/2020

   This project consists of placing 18 tons of 3" minus stone, 54 tons of macadam stone, 36 tons of class E riprap, a ditch cleanout, and other miscellaneous work. Send an email to request plans.

Contact:
Jason Kruse
(515) 250-3707
jason.kruse@dnr.iowa.gov




WARREN -- PROJECT # 20-05-91-02                4/30/2020                Small Project Letting
LAKE AHQUABI STATE PARK
CCC BRIDGE ABUTMENT REPAIR
Proposal Guarantee: $0
Completion Date: 8/31/2020

   This project consists of placing 135 tons of class D riprap to protect bridge abutments on a pedestrian bridge. Send an email to request plans.

Contact:
Jason Kruse
(515) 250-3707
jason.kruse@dnr.iowa.gov