BID LETTING RESULTS - October, 2015

 
 

The following are the results of bids received October, 2015 for projects which the Iowa Department of Natural Resources required to be constructed.  Should there be any discrepancies between the bids below and those provided and recorded in official bid tabs, the official bid tabs govern.
 

To see the Project Details for this Bid Letting Click Here .




CLINTON -- PROJECT # 13-06-23-02                10/15/2015                Small Project Letting
OTHER - GOOSE LAKE WMA
DIKE REPAIRS REBID
 
BIDS RECEIVED:
    Lansing Brothers Construction Co. Inc. 
$56,720.00 
    Eastern Iowa Excavating and Concrete, LLC 
$66,556.00 
    Miller Trucking & Excavating 
$77,900.00 
    CAJ Enterprises Inc. dba Chris Jones Trucking 
$79,387.96 
    Valley Construction Company 
$121,800.00 

full bid tab