APPANOOSE -- PROJECT # 15-05-04-02                10/9/2014                Small Project Letting
SEDAN BOTTOMS
REPAIR WEIR STRUCTURE
 
BIDS RECEIVED:
    Sterk Excavating Inc. 
$12,850.00 
    Hill Contracting 
$20,875.00 