The following are the results of bids received September, 2020 for projects which the Iowa Department of Natural Resources required to be constructed. Should there be any discrepancies between the bids below and those provided and recorded in official bid tabs, the official bid tabs govern.
To see the Project Details for this Bid Letting Click Here .
| POTTAWATTAMIE -- PROJECT # 20-04-78-04 9/17/2020 Large Project Letting
| LAKE MANAWA STATE PARK
| DAY-USE SECURITY GATES | | BIDS RECEIVED: |
American Fence Company
|
$92,273.26 |
|
| VAN BUREN -- PROJECT # 20-06-89-03 9/17/2020 Large Project Letting
| LACEY-KEOSAUQUA STATE PARK
| HAIL DAMAGE REPAIR | | BIDS RECEIVED: |
Iron Hill Contruction LLC
|
$153,373.00 |
Iowa Construction and Remodeling
|
$186,647.00 |
|
| VAN BUREN -- PROJECT # 20-06-89-03 9/17/2020 Large Project Letting
| LACEY-KEOSAUQUA STATE PARK
| HAIL DAMAGE REPAIR (CONTRACT) | | BIDS RECEIVED: |
Iron Hill Contruction LLC
|
$141,193.00 |
Iowa Construction and Remodeling
|
$183,690.00 |
|
| DICKINSON -- PROJECT # 20-01-30-17 9/17/2020 Small Project Letting
| EMERSON BAY STATE RECREATION AREA
| FISH CLEANING STATION SEPTIC TANK REPLACEMENT | | BIDS RECEIVED: |
Jeppesen Gravel
|
$7,025.00 |
Under Construction
|
$7,654.00 |
Schmitt Const Co
|
$9,550.00 |
|
| GUTHRIE -- PROJECT # 20-04-39-02 9/17/2020 Small Project Letting
| SAYLORVILLE WILDLIFE UNIT
| LAKIN SLOUGH CULVERT FLOW LINE ADJUSTMENT | | BIDS RECEIVED: |
Richards Construction Co., Inc.
|
$41,535.00 |
Progressive Structures LLC
|
$73,506.00 |
Gus Construction Co., Inc.
|
$104,305.00 |
|
|