The following are the results of bids received September, 2012 for projects which the Iowa Department of Natural Resources required to be constructed. Should there be any discrepancies between the bids below and those provided and recorded in official bid tabs, the official bid tabs govern.
To see the Project Details for this Bid Letting Click Here .
| ADAMS -- PROJECT # 13-04-02-01 9/13/2012 Small Project Letting
| MOUNT AYR FISHERIES MANAGEMENT UNIT
| | GATE REPAIR AT LAKE ICARIA | | | | BIDS RECEIVED: |
|
Hymbaugh Construction
|
$24,380.00 |
|
TEK Builders Inc
|
$25,300.00 |
|
C.L. Carroll Co., Inc.
|
$60,859.00 |

|
| CERRO GORDO -- PROJECT # 13-03-17-02 9/13/2012 Small Project Letting
| CLEAR LAKE STATE PARK
| | SHOWER FLOOR REPLACEMENT | | | | BIDS RECEIVED: |
|
MD Johnson Consulting
|
$3,380.00 |
|
Larson Contracting Central LLC
|
$7,899.00 |

|
| DELAWARE -- PROJECT # 13-03-28-01 9/13/2012 Small Project Letting
| BACKBONE STATE PARK
| | REPLACE BARN SIDING AND WINDOWS | | | | BIDS RECEIVED: |
|
Matt Construction Inc.
|
$14,316.00 |
|
Lansing Brothers Construction Co. Inc.
|
$18,150.00 |
|
Greenley Development Co.
|
$19,870.00 |
|
Jonas Raber Construction LLC
|
$20,343.22 |
|
Porter & Porter Construction LLC
|
$22,600.00 |
|
MD Johnson Consulting
|
$23,579.00 |
|
Hanson Construction LLC
|
$30,700.00 |

|
| SAC -- PROJECT # 13-01-81-02 9/13/2012 Small Project Letting
| BLACKHAWK LAKE
| | BLACKHAWK LAKE CONCRETE WEIR REPAIR | | | | BIDS RECEIVED: |
|
Midstates Builders, Inc
|
$20,000.14 |
|
Richards Construction Co. Inc.
|
$22,000.00 |

|
| WEBSTER -- PROJECT # 12-02-94-01 9/13/2012 Small Project Letting
| DOLLIVER STATE PARK
| | RV DUMP STATION & OTHER UPGRADES | | | | BIDS RECEIVED: |
|
Larsen Construction
|
$43,975.25 |
|
Jensen Builders, Ltd
|
$53,294.00 |
|
|