BID LETTING RESULTS - August, 2010

 
 

The following are the results of bids received August, 2010 for projects which the Iowa Department of Natural Resources required to be constructed.  Should there be any discrepancies between the bids below and those provided and recorded in official bid tabs, the official bid tabs govern.
 

To see the Project Details for this Bid Letting Click Here .




BLACK HAWK -- PROJECT # 09-03-07-11                8/26/2010                Small Project Letting
GEORGE WYTH STATE PARK
REPLACE PITVAULT (2) AND ADD NEW FLUSH TOILET
 
BIDS RECEIVED:
    Matt Construction Inc 
$88,529.29 

full bid tab