The following are the results of bids received August, 2010 for projects which the Iowa Department of Natural Resources required to be constructed. Should there be any discrepancies between the bids below and those provided and recorded in official bid tabs, the official bid tabs govern.
To see the Project Details for this Bid Letting Click Here .
| BENTON -- PROJECT # 10-06-06-01 8/19/2010 Small Project Letting
| DUDGEON LAKE WILDLIFE AREA
| | ANDERSON MARSH DIKE REPAIR | | | | BIDS RECEIVED: |
|
CAJ Enterprises Inc.
|
$8,505.86 |

|
| CERRO GORDO -- PROJECT # 10-03-17-06 8/19/2010 Small Project Letting
| CLEAR LAKE STATE PARK
| | PIT VAULT | | | | BIDS RECEIVED: |
|
Hanson Construction
|
$4,500.00 |
|
Burr Oak Springs Limited
|
$9,500.00 |

|
| DELAWARE -- PROJECT # 10-03-28-01 8/19/2010 Small Project Letting
| BACKBONE STATE PARK
| | PIT VAULT REPLACEMENT | | | | BIDS RECEIVED: |
|
Browns Pump Service
|
$2,000.00 |
|
Lansing Brothers Construction Co. Inc.
|
$2,940.00 |
|
Matt Construction Inc
|
$3,950.00 |
|
Burr Oak Springs Limited
|
$4,500.00 |
|
Tschigffrie Excavating Co
|
$5,880.00 |

|
| HARRISON -- PROJECT # 11-04-43-01 8/19/2010 Small Project Letting
| LOESS HILLS STATE FOREST
| | MOVE EXISTING STORAGE BUILDINGS | | | | BIDS RECEIVED: |

|
| MUSCATINE -- PROJECT # 08-06-70-05 8/19/2010 Small Project Letting
| WILDCAT DEN STATE PARK
| | NEW PARKING AND UTILITIES | | | | BIDS RECEIVED: |
|
Hy-Brand Industrial Contractors
|
$172,492.93 |
|
McCleary Excavating Co., Inc
|
$182,290.40 |
|
Riverbend Excavating Inc.
|
$204,011.45 |
|
Miller Trucking & Excav
|
$280,905.00 |
|
|