BID LETTING RESULTS - July, 2014

 
 

The following are the results of bids received July, 2014 for projects which the Iowa Department of Natural Resources required to be constructed.  Should there be any discrepancies between the bids below and those provided and recorded in official bid tabs, the official bid tabs govern.
 

To see the Project Details for this Bid Letting Click Here .




TAMA -- PROJECT # 14-05-86-05                7/10/2014                Small Project Letting
OTTER CREEK HEADQUARTERS
BUILDING IMPROVEMENTS
 
BIDS RECEIVED:
    Jonas Raber Construction LLC 
$52,516.00 
    Garling Construction, Inc 
$72,200.00 
    Hay Construction Services, Inc. 
$93,939.00 

full bid tab