The following are the results of bids received June, 2018 for projects which the Iowa Department of Natural Resources required to be constructed. Should there be any discrepancies between the bids below and those provided and recorded in official bid tabs, the official bid tabs govern.
To see the Project Details for this Bid Letting Click Here .
| CASS -- PROJECT # 18-04-15-01 6/28/2018 Small Project Letting
| LAKE ANITA STATE PARK
| CHECK-IN KIOSK | | BIDS RECEIVED: |
Caliber Concrete LLC
|
$24,998.00 |
|
| DELAWARE -- PROJECT # 18-06-28-02 6/28/2018 Small Project Letting
| MAQUOKETA WILDLIFE UNIT
| TAKES WETLAND RESTORATION | | BIDS RECEIVED: |
Dan Oberbreckling Concrete & Excavating
|
$28,080.00 |
LaGrange, Inc.
|
$33,340.00 |
VonBehren Excavating Inc.
|
$35,319.05 |
Donlon Brothers Construction LLC
|
$39,300.00 |
Burr Oak Springs
|
$52,000.00 |
Crane Construction
|
$64,200.00 |
B & J Hauling and Excavation Inc.
|
$68,709.50 |
Pirc-Tobin Construction, Inc.
|
$86,630.00 |
F.L. Krapfl Inc.
|
$97,056.00 |
|
| LUCAS -- PROJECT # 18-05-59-02 6/28/2018 Small Project Letting
| STEPHENS STATE FOREST
| SOUTH POND OUTLET REPLACEMENT | | BIDS RECEIVED: |
Savage Dirt Works, LLC
|
$46,260.00 |
Sterk Excavating Inc.
|
$49,567.28 |
RW Excavating Solutions LC
|
$83,639.00 |
|
|