The following are the results of bids received May, 2013 for projects which the Iowa Department of Natural Resources required to be constructed. Should there be any discrepancies between the bids below and those provided and recorded in official bid tabs, the official bid tabs govern.
To see the Project Details for this Bid Letting Click Here .
| POLK -- PROJECT # 14-05-77-03 5/1/2013 Large Project Letting
| STATE FAIR DNR BUILDING
| | BUILDING RENOVATIONS | | | | BIDS RECEIVED: |
|
Munro Construction Company
|
$151,400.00 |
|
BluePrint Homes LLC
|
$157,249.00 |
|
Blue Ribbon Builders
|
$198,336.00 |

|
| UNION -- PROJECT # 12-04-88-01 5/1/2013 Large Project Letting
| GREEN VALLEY STATE PARK
| | TRAIL CONSTRUCTION | | | | BIDS RECEIVED: |
|
Ag & Turf Construction LLC
|
$734,719.88 |
|
Carley Construction LLC
|
$753,366.40 |
|
Absolute Concrete Construction Inc
|
$848,000.00 |
|
Godbersen-Smith Construction Company Inc
|
$924,407.60 |
|
Jasper Construction Services Inc
|
$931,934.00 |
|
MPS Engineers
|
$999,748.00 |
|
|