BID LETTING RESULTS - April, 2013

 
 

The following are the results of bids received April, 2013 for projects which the Iowa Department of Natural Resources required to be constructed.  Should there be any discrepancies between the bids below and those provided and recorded in official bid tabs, the official bid tabs govern.
 

To see the Project Details for this Bid Letting Click Here .




GUTHRIE -- PROJECT # 13-04-39-06                4/23/2013                Small Project Letting
SPRINGBROOK
ED. CENTER WATER SYSTEM REPAIR
 
BIDS RECEIVED:
    Schoon Construction Inc 
$45,475.00 
    Hymbaugh Construction 
$56,780.00 