The following are the results of bids received March, 2013 for projects which the Iowa Department of Natural Resources required to be constructed. Should there be any discrepancies between the bids below and those provided and recorded in official bid tabs, the official bid tabs govern.
To see the Project Details for this Bid Letting Click Here .
| POLK -- PROJECT # 12-02-77-16 3/14/2013 Small Project Letting
| BIG CREEK
| | EAST BOAT RAMP EXTENSIONS | | | | BIDS RECEIVED: |
|
MPS Engineers
|
$20,088.00 |
|
Richards Construction Co., Inc.
|
$20,244.00 |

|
| WEBSTER -- PROJECT # 11-02-94-9 3/14/2013 Small Project Letting
| BRUSHY CREEK SRA
| | CONSTRUCT NEW 2 CAR GARAGE | | | | BIDS RECEIVED: |
|
Hanson Construction llc
|
$45,000.00 |

|
| WEBSTER -- PROJECT # 12-02-94-04 3/14/2013 Small Project Letting
| BRUSHY CREEK RECREATION AREA
| | DEMOLITION OF PK RES GARAGE | | | | BIDS RECEIVED: |
|
Campbell Electric
|
$7,675.00 |
|
Schoon Construction, Inc.
|
$8,250.00 |
|
Hanson Construction LLC
|
$10,500.00 |
|
MPS Engineers
|
$10,650.00 |
|
Richards Construction Co., Inc.
|
$11,000.00 |
|
Hansons Landscaping and Lawncare
|
$14,000.00 |
|
|