The following are the results of bids received January, 2020 for projects which the Iowa Department of Natural Resources required to be constructed. Should there be any discrepancies between the bids below and those provided and recorded in official bid tabs, the official bid tabs govern.
To see the Project Details for this Bid Letting Click Here .
| FAYETTE -- PROJECT # 18-03-33-01 1/30/2020 Small Project Letting
| VOLGA RIVER STATE RECREATION AREA
| | TREE CLEARING | | | | BIDS RECEIVED: |
|
Donlon Brothers Construction LLC
|
$14,200.00 |
|
David Ryan Construction
|
$23,082.50 |
|
Skyline Construction Inc.
|
$29,005.00 |
|
Matt Construction, Inc.
|
$29,630.00 |
|
Crane Construction
|
$31,600.00 |
|
Cornwell Construction & Excavation
|
$75,999.91 |
|
Smith Landworx
|
$194,150.00 |

|
| SAC -- PROJECT # 20-02-81-03 1/30/2020 Small Project Letting
| BLACK HAWK STATE PARK
| | CULVERT REPAIR | | | | BIDS RECEIVED: |
|
Spring Lake Construction
|
$6,640.00 |
|
Richards Construction Co., Inc.
|
$10,380.00 |
|
Vicker Drlling LLC
|
$15,030.00 |
|
Reding's Gravel & Excavating Co. Inc.
|
$17,370.00 |
|
|