The following are the results of bids received December, 2019 for public improvement projects which the Iowa Department of Natural Resources requires to be constructed. The results included below are the bids that were received timely. Consistent with the Specifications Manual, in the event of a discrepancy between a unit price, extensions or total amounts of bid, the unit price proposed by the bidder has been used to accurately calculate the total price based on the quantities identified in the project specifications.
NO DETERMINATION HAS BEEN MADE BY THIS PUBLICATION AS TO WHICH BID, IF ANY, IS THE LOWEST RESPONSIBLE, RESPONSIVE BID. THE DNR RESERVES THE RIGHT, AFTER REVIEW OF THE BIDS SUBMITTED, TO AWARD A CONTRACT FOR THE PROJECTS LISTED BELOW TO THE ENTITY SUBMITTING THE LOWEST RESPONSIBLE, RESPONSIVE BID OR TO REJECT ALL BIDS.
View Project Details for this Bid Letting
| DELAWARE -- PROJECT # 20-03-28-04 12/12/2019 Large Project Letting
| BACKBONE STATE PARK
| ENTRY PORTALS | | BIDS RECEIVED: |
Matt Construction, Inc.
|
$56,189.00 |
Gruss Construction LLC
|
$75,800.00 |
Under Construction
|
$77,010.00 |
Boomerang Corp
|
$83,100.00 |
Woodruff Construction, LLC
|
$89,400.00 |
|
| CERRO GORDO -- PROJECT # 18-03-17-04 12/5/2019 Small Project Letting
| LEKWA MARSH WMA
| PEDELTY WETLAND RESTORATION (REBID) | | BIDS RECEIVED: |
A1 Excavating & Drainage Inc.
|
$48,175.00 |
Dan Oberbreckling Concrete & Excavating
|
$59,500.00 |
David Ryan Construction
|
$59,743.00 |
Green Rain
|
$59,950.00 |
Midwest Concrete & Excavating LLC
|
$69,600.00 |
Groves Contracting LLC
|
$79,025.00 |
Yohn Co
|
$79,720.00 |
Peters Excavation and Rental LLC
|
$348,586.00 |
The following apparent low bidders were found to be Non-Responsive and/or Not Responsible. No determinations have been made regarding the Responsiveness and Responsibility of the bidders that are not the apparent low. Midwest Liquidation, LLC
DNR reserves the right to modify this list as it reviews and inspects the bids received. DNR will update the bid tab accordingly.
|
| LUCAS -- PROJECT # 20-05-59-04 12/19/2019 Small Project Letting
| RATHBUN WMA
| NORTH COLYN - BRIDGE DECK | | BIDS RECEIVED: |
Haworth Land Construction
|
$19,846.18 |
Dingman Const.
|
$22,648.00 |
Sterk Excavating Inc
|
$23,500.00 |
Gruss Construction LLC
|
$24,763.00 |
Boulder Contracting LLC
|
$29,000.00 |
|
| LUCAS -- PROJECT # 20-05-59-06 12/19/2019 Small Project Letting
| STEPHENS STATE FOREST
| ROOF ON OFFICE HEADQUARTERS | | BIDS RECEIVED: |
Wolf Construction Services Inc.
|
$18,590.00 |
Rubel Roofing and Construction
|
$19,570.00 |
Iron Hill Contruction LLC
|
$19,910.00 |
Gruss Construction LLC
|
$21,629.00 |
LSS Inc dba Haus Roofing and Construction Services
|
$23,840.00 |
Vicker Drlling LLC
|
$24,600.00 |
|
|