The following are the results of bids received November, 2016 for public improvement projects which the Iowa Department of Natural Resources requires to be constructed. The results included below are the bids that were received timely. Consistent with the Specifications Manual, in the event of a discrepancy between a unit price, extensions or total amounts of bid, the unit price proposed by the bidder has been used to accurately calculate the total price based on the quantities identified in the project specifications.
NO DETERMINATION HAS BEEN MADE BY THIS PUBLICATION AS TO WHICH BID, IF ANY, IS THE LOWEST RESPONSIBLE, RESPONSIVE BID. THE DNR RESERVES THE RIGHT, AFTER REVIEW OF THE BIDS SUBMITTED, TO AWARD A CONTRACT FOR THE PROJECTS LISTED BELOW TO THE ENTITY SUBMITTING THE LOWEST RESPONSIBLE, RESPONSIVE BID OR TO REJECT ALL BIDS.
View Project Details for this Bid Letting
| UNION -- PROJECT # 17-04-88-02 11/10/2016 Large Project Letting
| THREE MILE LAKE
| SHORELINE STABILIZATION | | BIDS RECEIVED: |
Tri-Smith Construction LLC
|
$716,287.04 |
TK Concrete, Inc.
|
$771,501.00 |
Peterson Contractors, Inc.
|
$796,377.25 |
Murphy Heavy Const.
|
$853,144.20 |
Empire Construction and Trenching, Inc.
|
$873,062.91 |
Michael J. Lamb dba Lamb Tiling
|
$915,505.00 |
Minturn, Inc.
|
$917,016.00 |
Reilly Construction Co., Inc.
|
$999,710.00 |
Boyd Construction, LLC
|
$1,072,054.60 |
|
| LEE -- PROJECT # 16-06-56-01 11/10/2016 Small Project Letting
| PRAIRIE RESOURCE CENTER
| GREENHOUSE REPLACEMENT | | BIDS RECEIVED: |
Hennigar Construction LC
|
$68,066.57 |
Kingdom Construction
|
$71,700.00 |
|
| RINGGOLD -- PROJECT # 17-04-80-01 11/10/2016 Small Project Letting
| MOUNT AYR FISHERIES MANAGEMENT UNIT
| MT. AYR FISH HATCHERY WATERLINE | | BIDS RECEIVED: |
Schaefer Excavating, Inc.
|
$35,516.50 |
Valley Plumbing
|
$57,891.40 |
|
| RINGGOLD -- PROJECT # 17-04-80-02 11/10/2016 Small Project Letting
| MOUNT AYR FISHERIES MANAGEMENT UNIT
| REPAIR FOGLE LAKE JETTIES | | BIDS RECEIVED: |
Schaefer Excavating, Inc.
|
$20,090.00 |
JNC Construction, LLC
|
$20,397.50 |
Jeff Sickels Dozing LLC
|
$23,500.00 |
Michael J. Lamb dba Lamb Tiling
|
$28,900.00 |
|
| JACKSON -- PROJECT # 15-06-49-01 11/17/2016 Small Project Letting
| BELLEVUE STATE PARK
| LAGOON VALVE REPLACEMENT | | BIDS RECEIVED: |
F.L. Krapfl, Inc.
|
$7,600.00 |
Ihrig Works LLC
|
$9,600.00 |
Connolly Construction Inc
|
$9,733.60 |
SCG, LLC
|
$14,000.00 |
|
| JASPER -- PROJECT # 16-05-50-02 11/17/2016 Small Project Letting
| ROCK CREEK
| ADA PATHWAY TO FISHING PIER | | BIDS RECEIVED: |
Boulder Contracting, LLC
|
$24,256.00 |
Strand Excavating Inc
|
$30,137.80 |
Hatch Grading & Contracting Inc.
|
$38,170.80 |
Jasper Construction Services, Inc.
|
$46,775.00 |
|
| POLK -- PROJECT # 17-02-77-01 11/17/2016 Small Project Letting
| BIG CREEK
| GRADE STABILIZATION STRUCTURE | | BIDS RECEIVED: |
Benner Trucking & Dozing
|
$25,275.31 |
Nagle Land Tiling Inc
|
$33,203.50 |
RW Excavating & Dozing
|
$35,414.80 |
Richards Construction Co., Inc.
|
$44,660.00 |
|
|