The following are the results of bids received November, 2015 for public improvement projects which the Iowa Department of Natural Resources requires to be constructed. The results included below are the bids that were received timely. Consistent with the Specifications Manual, in the event of a discrepancy between a unit price, extensions or total amounts of bid, the unit price proposed by the bidder has been used to accurately calculate the total price based on the quantities identified in the project specifications.
NO DETERMINATION HAS BEEN MADE BY THIS PUBLICATION AS TO WHICH BID, IF ANY, IS THE LOWEST RESPONSIBLE, RESPONSIVE BID. THE DNR RESERVES THE RIGHT, AFTER REVIEW OF THE BIDS SUBMITTED, TO AWARD A CONTRACT FOR THE PROJECTS LISTED BELOW TO THE ENTITY SUBMITTING THE LOWEST RESPONSIBLE, RESPONSIVE BID OR TO REJECT ALL BIDS.
View Project Details for this Bid Letting
| APPANOOSE -- PROJECT # 15-05-04-9 11/12/2015 Large Project Letting
| RATHBUN FISHERIES MANAGEMENT UNIT
| HOUSE RENOVATIONS | | BIDS RECEIVED: |
Hymbaugh Construction
|
$80,664.00 |
|
| DELAWARE -- PROJECT # 16-03-28-02 11/12/2015 Large Project Letting
| BACKBONE STATE PARK
| SHOWER BUILDING REPLACEMENT | | BIDS RECEIVED: |
F.L. Krapfl Inc.
|
$247,172.50 |
Portzen Construction, Inc.
|
$262,167.50 |
Matt Construction Inc.
|
$282,750.00 |
Miller Trucking & Excavating
|
$305,575.00 |
|
| JACKSON -- PROJECT # 15-06-49-04 11/12/2015 Large Project Letting
| BELLEVUE STATE PARK
| SHOWER BUILDING REPLACEMENT | | BIDS RECEIVED: |
F.L. Krapfl Inc.
|
$243,378.50 |
Portzen Construction, Inc.
|
$253,204.50 |
Miller Trucking & Excavating
|
$315,350.00 |
|
| POLK -- PROJECT # 15-05-77-06 11/12/2015 Large Project Letting
| RED ROCK WILDLIFE UNIT
| RUNNELLS MARSH BOAT ACCESS | | BIDS RECEIVED: |
RW Excavating & Dozing
|
$72,804.00 |
Hymbaugh Construction
|
$82,748.00 |
Gruss Construction LLC
|
$96,790.00 |
Strand Excavating Inc
|
$100,309.00 |
Jensen Construction Company
|
$118,146.00 |
J & K Contracting LLC
|
$133,300.00 |
The following apparent low bidders were found to be Non-Responsive and/or Not Responsible. No determinations have been made regarding the Responsiveness and Responsibility of the bidders that are not the apparent low. TK Concrete, Inc.
DNR reserves the right to modify this list as it reviews and inspects the bids received. DNR will update the bid tab accordingly.
|
| RINGGOLD -- PROJECT # 15-04-80-02 11/12/2015 Large Project Letting
| MOUNT AYR FISHERIES MANAGEMENT UNIT
| WALNUT CREEK MARSH RESTORATION REBID | | BIDS RECEIVED: |
Lamb Tiling
|
$70,435.50 |
Jeff Sickels Dozing LLC
|
$78,480.00 |
Superior Seawalls Inc.
|
$166,280.50 |
The following apparent low bidders were found to be Non-Responsive and/or Not Responsible. No determinations have been made regarding the Responsiveness and Responsibility of the bidders that are not the apparent low. William Godden dba Godden Construction
DNR reserves the right to modify this list as it reviews and inspects the bids received. DNR will update the bid tab accordingly.
|
| TAMA -- PROJECT # 16-05-86-01 11/12/2015 Large Project Letting
| UNION GROVE STATE PARK
| VALVE REPLACEMENT AND FISH BARRIER | | BIDS RECEIVED: |
Jasper Construction Services, Inc.
|
$132,950.00 |
M-Z Construction Inc.
|
$144,800.00 |
J & K Contracting LLC
|
$152,440.00 |
Weidner Construction, Inc.
|
$154,625.00 |
|
| CERRO GORDO -- PROJECT # 16-03-17-01 11/19/2015 Small Project Letting
| CLEAR LAKE STATE PARK
| REPLACE DUMP STATION SEWER LINE | | BIDS RECEIVED: |
Larson Contracting Central, LLC
|
$6,693.00 |
Jeppesen Gravel
|
$8,085.00 |
Beemer Companies
|
$14,051.25 |
Hymbaugh Construction
|